8. OPERATING PROCEDURES
NOTE!
Before carrying out any operations on the unit read the Safety standards chapter carefully.
NOTE!
While a procedure is being performed, the switches' closing/opening need to be confirmed by pressing the ENTER button.
8-1
Example of procedure step
ůŽƐĞĂƩĞƌLJ
NOTE!
For the position of the switches refer to the OVERVIEW chapter.
NOTE!
For the cabling of the UPS refer to the CONNECTION chapter.
8.1. SWITCHING
ON
• Supply power to the UPS
• Put switch
Q1
into position
ON
.
• Wait for the display to switch on.
• Enter
MAIN MENU > CONTROLS > START PROCEDURE
.
• Carry out the operations indicated on the display.
8.2. SWITCHING
OFF
This operation interrupts the power supply to the load. The UPS and the battery charger will be shut down.
• Enter
MAIN MENU > CONTROLS > STOP PROCEDURE
.
• Wait 2 minutes for the UPS shutdown. A countdown shows the remaining seconds.
NOTE!
The controlled shutdown of each server connected to the LAN can be managed by shutdown software.
Refer to the NETVISION chapter.
• Carry out the operations indicated on the display.
Confi rm and go to next step
Request to fulfi ll
Abort procedure