background image

GT INSTALLATION AND OPERATION INSTRUCTIONS

Page 16

Safe lighting and other performance criteria were met 
with the gas manifold and control assembly provided on 
the boiler when the boiler underwent tests specifi ed in 
ANSI Z21.13/CSA 4.9. All gas connections MUST be leak 
tested before putting the boiler into operation.

WARNING: Never use an open fl ame to test for 
gas leaks. Always use an approved leak detection 
method. Failure to comply with this WARNING 
could result in an explosion!

Table 4 - Gas Pipe Capacity

  
 

Nominal 

    

Pipe Length

  Iron Pipe 

10'  

20'  

30'  

40'  

50'  

60'  

80'   100'   150'

 Size 

 

 

 Gas Pipe Capacity (ft

3

/hr)

 

3/4"  

278   190   152   130   115   105   90  

79  

64

 

1"  

520   350   285   245   215   195  170  150  120

 

1 1/4"  

1050   730   590   500   440   400   350   305   250

 

1 1/2”  

1600  1100   890   760   670   610   530   460   380

Note: Maximum pipe capacity in ft

3

/hr is based on a 0.60 specifi c gravity 

gas at a pressure of 0.5 psig and a 0.3" WC pressure drop.

Table 5 - Equivalent Pipe Length Chart

   

 Nominal 

Type of Pipe Fitting

 Iron 

90°

 

Tee  

Gate Valve  

Gas Cocks

 

 Pipe 

 

(branch 

fl ow)  (full port)

 Size 

Equivalent length of pipe fi ttings in feet

 

3/4"  

2.06  

4.12  

0.48  

1.25

 

1"  

2.62  

5.24  

0.61  

1.60

 

1 1/4"  

3.45  

6.90  

0.81  

2.15

 

1 1/2"  

4.02  

8.04  

0.94  

2.50

Whenever the gas supply piping is pressure tested the 
boiler gas controls must be protected. If the test pressure 
is equal to, or less than 

1/2 psi

3.5 kPa

, isolate the boiler 

by closing it’s manual shut off valve, see Figure 27. If the 
test pressure is greater than 

1/2 psi

3.5 kPa

, disconnect 

the boiler and it’s individual shut-off valve from the gas 
supply piping.

WARNING: Failure to protect the gas valve from 
excessive pressure can damage the gas valve 
which can cause a fi re or explosion!

GAS SUPPLY PIPING

The GX hot water boiler comes from the factory ready 
to be piped to the gas supply. The National Fuel Gas 
Code, ANSI Z223.1/NFPA 54 and local codes for gas 
piping requirements and sizing must be followed. If for 
any reason the boiler is not for the type of gas available 
at the installation site, call the nearest Smith distributor 
to resolve the problem.

Figure 27 depicts the proper way to connect the boiler to 
the gas supply piping. The manual shut-off valve MUST be 
installed in the supply piping. It should be approximately 

5 ft

1.5 m

, above the fl oor. Provide a sediment trap/drip 

leg at the bottom of the vertical section of the gas supply 
pipe. A ground joint union should be installed between 
the boiler gas controls and the supply piping. Each of 
these items is needed to ensure long life and ease of 
servicing. Always use a pipe sealant that is suitable for 
use with LP gas. Flexible gas piping is recommended if 
accepted by the local codes. Make sure the gas piping 
doesn’t hinder boiler access.

CAUTION: Always use a wrench on the gas valve 
body when making gas connections to it. Never over-
tighten the piping entering the gas valve body or the 
gas valve will be damaged voiding the warranty!

CAUTION:  The gas piping must be properly supported 
by the building structure and not by the boiler or the 
gas valve will be damaged voiding the warranty!

Figure 27 - Gas Supply Piping

Table 4 should be used to ensure that the gas supply 
piping is sized properly. If more than one appliance is 
supplied by the same supply pipe, the piping must be 
sized based on the maximum possible demand. Do not 
neglect the pressure drop due to pipe fi ttings. Table 5 
should be used in conjunction with Table 4 to ensure that 
the gas supply piping is sized properly.

Summary of Contents for GT-150

Page 1: ...NING If the information in this manual is not followed exactly a fire or explosion may result causing property damage personal injury or loss of life INSTALLER THESE INSTRUCTIONS MUST BE AFFIXED ADJAC...

Page 2: ...d long life for which this boiler was designed these instructions must be read understood and followed Direct all questions to your Smith distributor or to the Customer Service Department 260 North El...

Page 3: ...however 24 in 610 mm is recommended 2 An optimum site will be level central to the hot water piping system and close to an outside wall NOTE This boiler is designed for direct placement on a combustib...

Page 4: ...let System Attachment One of the following materials is to be used for the air intake pipe 3 in 76 mm ABS 3 in 76 mm PVC Sch 40 pipe 3 in 76 mm Galvanized Steel pipe See Table 2 for the maximum equiva...

Page 5: ...mm vent collar to 3 in 76 mm at the boiler Figure 3 Figure 3 Vent Pipe To Boiler Attachment The maximum combined equivalent vent and intake pipe lengths are listed in Table 2 The length specified is t...

Page 6: ...liance will produce a plume of water vapor and should be taken into consideration when selecting an adequate vent terminal location A 3 ft 0 9 m diameter stainless plastic or vinyl shield can be used...

Page 7: ...lations that have to exit the foundation below grade excavate the site as shown in Figure 8 to a point below where the pipes exit the building Maintain the proper vent clearances as outlined above Att...

Page 8: ...ditions must apply 1 If limited to two terminals the horizontal centerline distance must be 4 in 102 mm or greater than 24 in 610 mm to prevent flue gas recirculation For more than two terminals locat...

Page 9: ...terminal must always be a minimum of 12 in 305 mm plus the snow allowance above any surface that will support snow however a snow allowance of 24 in 610 mm is highly recommended Figures 15 16 Consult...

Page 10: ...nsure that the air inlet and vent system lengths are within the maximums specified in Table 2 The debris screens provided with the boiler must be installed in both the air intake and vent terminals In...

Page 11: ...e products such as Fernox Superfloc for new installations and CHR Central Heating Restorer for retrofits Also add an inhibitor to the system water to prevent limestone and magnetite deposits from form...

Page 12: ...diagram to be used as a vacuum breaker and to eliminate air upon filling Figure 21 LWCO Air Vent Piping PRIMARY LOOP PLUMBING This low mass boiler requires a continuous minimum water flow for proper...

Page 13: ...terminals C1 L2 5 See Table 3 for Indirect Water Heater pump flow requirements This pump is wired to terminals AP L2 6 Set pressure reducing valve to 12 psi 83 kPa 7 Use 30 psi 207 kPa relief valve ma...

Page 14: ...nals C1 L2 5 See Table 3 for Indirect Water Heater pump flow requirements This pump is wired to terminals AP L2 6 Set pressure reducing valve to 12 psi 83 kPa 7 Use 30 psi 207 kPa relief valve max Loc...

Page 15: ...tiple Zones Using Pumps Figure 26 Secondary Loop For Multiple Zones Using A Bypass Valve Note Velocity noise may be a problem when the entire output of the system pump is flowing through the zone with...

Page 16: ...he gas valve which can cause a fire or explosion GAS SUPPLY PIPING The GX hot water boiler comes from the factory ready to be piped to the gas supply The National Fuel Gas Code ANSI Z223 1 NFPA 54 and...

Page 17: ...ps with a maximum inrush of 6 amps If the amp draw of the pumps exceeds these maximums a pump controller or isolation relay must be used to prevent damage to the boiler Damage caused by improper wirin...

Page 18: ...uit between terminals T and C shutting down the pumps and the burner Multiple Zones w Taco Valve Controller Models ZVC403 to ZVC 406 Figure 31 shows the basic multiple zoned system using normally clos...

Page 19: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 19 Figure 30 Multiple 4 Wire Zone Valves...

Page 20: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 20 Figure 31 Multiple Zones w Taco Valve Controller Models ZVC403 to ZVC 406...

Page 21: ...on the pump controller The controller energizes the appropriate circulating pump and closes the circuit between terminals T and C on the Sentry 2100 control The Sentry 2100 provides power to the prima...

Page 22: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 22 Figure 33 Boiler Ladder Diagram...

Page 23: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 23 Figure 34 Boiler Connection Diagram...

Page 24: ...GT will maintain by increasing or decreasing the input Indirect Water Heaters The Sentry 2100 comes with an input and output for a 120 volt indirect pump When the A and C terminals are closed dry cont...

Page 25: ...ter Error Code On Off NOTE LFS must not be set below 48 on the GT150 model To start the control operation return to RUN on the menu and press Function Normal operation will begin Recommended Settings...

Page 26: ...C 70 F 21 C 1 85 RESET TEMPERATURE HICalc RES Outdoor Air x Reset Ratio RES 70 F 21 C 32 F 0 C x 1 85 70 F 21 C 70 6 F 21 C 70 F 21 C 140 6 F 42 C NOTE The design temperature is 0 F 18 C outside air...

Page 27: ...mmediately call a qualified service technician to inspect the appliance and to replace any part of the control system and any gas control that has been under water NOTE The GT was tested with Natural...

Page 28: ...ystem by turning the thermostat to it s lowest setting and then back to where it was or by momentarily interrupting the electrical power to the boiler D With the burner in operation close the manual s...

Page 29: ...r Immediately call a qualified service technician to inspect the appliance and to replace any part of the control system and any gas control that has been under water 1 STOP Read the safety informatio...

Page 30: ...s up to 2000 ft 610 m At elevations above 2000 ft 610 m input ratings should be reduced by 4 for each 1000 ft 305 m above sea level Check the input rate as follows NATURAL GAS 1 Turn off all other gas...

Page 31: ...ing at the valve Figure 2 6 Remove the nuts used to attach the burner to the heat exchanger 7 Carefully slide the burner out of the unit 8 Inspect the burner for damage or signs of deterioration Use a...

Page 32: ...bolts 7 Once the unit is level install the bottom two 14 3 lag bolts 8 Remove the Air Inlet Pipe assembly and Metering elbow from the gas valve venturi assembly Figure 44 Figure 44 Air Inlet Pipe Remo...

Page 33: ...calculated using formula in Section 8 1 If the thermostat demand light is turning off the thermostat has satisfied 2 If DHW temp light is turning off the aquastat or call for domestic has been satisfi...

Page 34: ...fan is running air switch may be faulty 4 If fan is not running check 120V wiring to blower if ok remove low voltage harness from blower if blower fails to start replace blower if blower does start p...

Page 35: ...gas valve when it opens If boiler lights check for flame signal between FC1 And FC2 on Fenwal control If lower then 1 2 micro amps see Boiler will not stay lit below Check combustion properties If the...

Page 36: ...vent from the boiler during ignition if unit lights smoothly with intake vent disconnected reconnect and check for proper combustion if unit maintains smooth operation after ignition Calibrate for pr...

Page 37: ...ure the resistance of the thermister when disconnected 2 Using the appropriate chart find the resistance and move vertically for the water probe or horizontally for the air probe until the line is int...

Page 38: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 38 Figure 48 Replacement Parts Exploded View SIOM 36...

Page 39: ...8 1 1 24 2 Clamp GT 82100 1 1 25 Sentry 2100 Control GT 82013 1 1 26 Complete Control Panel Assy GT 82754 1 1 27 PCB Optocoupler GT 82754 1 1 1 28 Outdoor Air Sensor 10K GT 81027 1 1 1 29 Transformer...

Page 40: ...WESTCAST INC 260 NORTH ELM STREET WESTFIELD MA 01085 TEL 413 562 9631 FAX 413 562 3799...

Reviews: