Figure 9 - External Air Intake and Vent Systems
The debris screens provided with the boiler must be
installed in both the air intake and vent terminals. Install
the screens in the outer most opening then glue a
1 in
,
25 mm
length of pipe into the opening to retain them,
Figure 10.
Figure 10 - Debris Screen Installation
Concentric Air Intake and Vent Terminal
If a concentric terminal is used it must be Smith part
number GT-82666 or York part number 1CT0303. The
concentric terminal must be located at least
12 in
,
305
mm
, above the normal snow line, Figure 11. Position the
air intake pipe on the top or to the side to prevent rain
from entering the boiler, Figure 13.
When terminals from multiple boiler installations exit a
common wall the following conditions must apply:
1. If limited to two terminals the horizontal centerline
distance must be
4 in
,
102 mm
, or greater than
24 in
,
610 mm
, to prevent flue gas recirculation.
For more than two ter minals located along a
horizontal plane, the centerline distance between
them must be
24 in
,
610 mm
, Figure 11.
2. If the terminals are located in a vertical plane the
centerline distance between them must be at least
48 in
,
1220 mm
, Figure 12.
Figure 11- Horizontal Concentric Terminal Location
Figure 12 - Vertical Concentric Terminal Location
When penetrating an outside wall the concentric terminal
must be constrained as shown in Figure 13. The opening
through which the concentric terminal passes must be
properly sealed to prevent products of combustion from
entering the building.
The air intake of the boiler must
be connected to the terminal!
WARNING: Failure to properly install and seal the
concentric terminal can result in excessive levels
of carbon monoxide which can cause severe
personal injury or death!
Summary of Contents for GT-150
Page 19: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 19 Figure 30 Multiple 4 Wire Zone Valves...
Page 22: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 22 Figure 33 Boiler Ladder Diagram...
Page 23: ...GT INSTALLATION AND OPERATION INSTRUCTIONS Page 23 Figure 34 Boiler Connection Diagram...
Page 40: ...WESTCAST INC 260 NORTH ELM STREET WESTFIELD MA 01085 TEL 413 562 9631 FAX 413 562 3799...