10 COMMISSIONING
Before operation, inspections that are recommended as follows should be carried
out:
1) Check and assure that all connections are correct, and that diameter of line is
suitable;
2) The DC power supply of controller is equipped with fuse, and the positive
supply (+Ve) and negative supply (-Ve) connected with battery are connected
correctly;
3) The emergency stop input is connected with the positive supply (+Ve) of the
battery through the NC terminal and fuse of emergency stop button;
4) The suitable operation should be taken to prevent the engine from crank
success (such as dismantling the connection of fuel), check and assure that it
is correct, then connect with battery, select manual mode, the controller will
execute program;
5) Press down the starting button on the panel of controller , the engine will crank,
after starts have been carried out according to setting crank numbers, the
controller sends the signal that indicates crank failure; Press the Stop/Reset
key to make the controller resetting;
6) Restore the measure that prevents the engine from crank success (such as
restoring the connection of fuel), press down the starting button again, the
engine will crank, if crank is normal, the genset will operate from idle operation
(if idle has been set) to normal operation. In the meantime, observe the
operation situation of engine and the voltage and frequency of the AC genset.
If there is abnormal, stop the genset, then check connections of each part
according to this handbook;
7) Select automatic state through front panel, then switch on the mains voltage,
the controller switches over ATS (if it exist) to mains on load after pass through
the mains normal delay, after cooling time, and then shut down to go into
standby state until the mains is abnormal again;
8) After the mains is abnormal again, the Genset will automatically crank into
normal operation state, and then close genset relay, control the ATS to switch
transfer to genset on load. If the situation is not same as described above,
check the connection of control part of the ATS according to this handbook;
9) If there are other questions, please contact the technical personnel of
Smartgen immediately.