8
Manually Controlling the Generator
8.1
Starting the Generator with Sunny Remote Control
Requirements:
☐ The Sunny Island must be able to control the generator via a control cable.
☐ The Sunny Remote Control must be in standard mode or user mode.
Procedure:
1. Select the
Generator
display page on the Sunny Remote Control and press the button (see Section 5.3.2
"Displaying Parameters and Operating and Setting the System", page 30).
2. To start the generator and run it permanently, select the parameter
Mode
and set to
Start
.
☑ The electricity generator starts and runs until you stop it again.
3. To start the generator and run it for one hour, select the parameter
Mode
and set to
Run1h
.
☑ The generator starts. If there is no generator request after one hour, the Sunny Island stops the generator.
8.2
Stopping the Generator with Sunny Remote Control
Risk of crushing injuries due to moving PV array parts
Moving parts in the PV array can crush or sever body parts. A generator can be started automatically by the
Sunny Island.
• Operate the generator only with the safety equipment.
• Carry out work on the generator in accordance with the manufacturer's specifications.
Requirements:
☐ The Sunny Island must be able to control the generator via a control cable.
☐ The Sunny Remote Control must be in standard mode or user mode.
Procedure:
1. Select the
Generator
display page on the Sunny Remote Control and press the button (see Section 5.3.2
"Displaying Parameters and Operating and Setting the System", page 30).
2. Select the parameter
Mode
and set to
Stop
.
☑ The generator is stopped temporarily. The generator restarts when a generator request is issued in automatic
generator mode and the minimum stop time has elapsed.
3. To stop the generator permanently, deactivate the automatic generator mode:
• Switch to installer mode on the Sunny Remote Control (see Section 5.4.1, page 32).
• Select the parameter
235.01 GnAutoEna
and set to
Disable
.
☑ The generator is permanently stopped.
8.3
Starting the Generator without Autostart Function
1. Start the generator (see manufacturer's manual).
2. Close the load-break switch between the generator and Sunny Island.
☑ After the warm-up period, the Sunny Island connects the stand-alone grid to the generator.
8 Manually Controlling the Generator
SMA Solar Technology AG