Page 30
December 2007
SJ 63AJ
It is the responsibility of the operator to read, completely understand and follow all instructions and warnings
contained in this operating manual and on the aerial platform.
F
AMILIARIZA
TION
2.4-2 Test Charge Indicator
1.
Ensure both “
” emergency stop buttons are
pulled out.
2.
In engine compartment, turn main power
disconnect switch to “ ” on position.
Result:
Charge indicator needle should move and
stay within the green area.
Charge Indicator Levels
Green:
This means that battery is adequately
charged. No action required. This also indicates
that charging system is working properly.
Yellow or Red:
This indicates undercharge status.
If charge indicator level is reasonably within
yellow or red area, start engine and recharge
battery before using any elevating function. After
recharging battery for 15 - 30 minutes, turn engine
off and ensure charge indicator needle is now in
green area.
WARNING
If charge indicator needle is still within
yellow or red area, inspect battery and
charging system for fault, and do not
elevate boom because emergency
lowering system may not function
properly.
NOTE
Close all cowlings before proceeding to
next item.
2.4-3 Base Control Console
1.
On platform control console, pull out “
”
emergency stop button.
WARNING
Ensure that you maintain three points
of contact to mount/dismount platform.
• Test Base Emergency Stop Light
1. On base control console, pull out
“
” emergency stop button.
Result:
Emergency stop light should
continuously illuminate. Glow plug light
should turn on and turn off after a slight
delay.
2. Turn off/base/platform (base/off/platform)
key switch to “
” base position.
3. Start engine by selecting “
” start
position from start/function enable/
emergency power switch.
Base Control Console
HOUR METER
QUARTZ
COUNTER
Off/Base/Platform
Key Switch
Emergency
Stop
HOUR METER
QUARTZ
COUNTER
Base/Off/Platform
Key Switch
Emergency
Stop
Start/Function
Enable/
Emergency
Power Switch
Function Tests
Section 2 - Familiarization