5. Site installation handover
Complete VersiCharge 175 kW Fast Charger System
Installation Checklist and attach photos of the installation.
5.1 Pre-checks
1. Check strain relief on power cables.
2. Check earths are attached on removable panels and
doors.
3. Check if there is any remaining liquid or dust and clean
the site.
5.2 Polarity, cross-wire and bolted short test
5.2.1 DC link test
1. Use a DMM and a long piece of wire to perform a
continuity test between each of the items in the
following table:
User Unit
Power Unit
Pass Criteria
Earth
DC +
NC
DC -
NC
Earth
Connected
DC +
DC +
Connected
DC -
NC
Earth
NC
DC -
DC +
NC
DC -
Connected
Earth
NC
5.2.2 AC link test
1. Use a DMM and a long piece of wire to perform a
continuity test between each of the items in the
following table:
Power Unit
(Isolation Switch)
Upstream Supply
Pass Criteria
Earth
L1
NC
L2
NC
L3
NC
Earth
Connected
L1
L1
Connected
L2
NC
L3
NC
Earth
NC
L2
L1
NC
L2
Connected
L3
NC
Earth
NC
L3
L1
NC
L2
NC
L3
Connected
Earth
NC
5.2.3 Waste management, tidy up and report
1. Finalize any waste pick up, cleaning operations, and tidy
up the site.
2. Send the full report to Siemens and all other parties
involved via VersiCharge 175 kW Fast Charger System
Installation Checklist and the pictures to support the
signed checklist.