Figure 6: IPU Cable Entry Diagram
After the foundation is prepared:
1. Ensure that all cables are pulled and labeled correctly
according to the cabling plan.
Notes:
• Ensure that the cables and cable glands are sealed
under the metal plate. If not, use Nofirno Cable Sealant
to seal.
• For more information, see VersiCharge 175 kW Fast
Charger Piping and Cabling.
2. Cut the mounting rods down to 50mm above the
foundation ground.
3. Deburr, then straighten threads.
4. Clean the slab of dust and debris.
5. Apply anti-seize to rods and temporarily fasten with an
M12 nut and flat washer.
Site Installation Manual
| VersiCharge Ultra 175™ kW Fast Charger
15