BA 2030 (2KJ4)
Operating Instructions, 07/2020, A5E50009094A/RS-AL
47
Commissioning
5
5.1
General information for commissioning
WARNING
Unintentional starting of the drive component
Secure the drive component to prevent it from being started up unintentionally.
Attach a warning notice to the start switch.
WARNING
Risk of slipping on oil
Remove any oil spillage immediately with an oil-binding agent in compliance with
environmental requirements.
Checking the pressure breather valve
Check that the breather valve is activated.
If the breather valve has a transport fixture, it must be removed before commissioning.
Figure 5-1
Pressure breather valve with securing clip
Remove the transport fixture by pulling the securing clip
①
in the direction of the arrow.
5.2
Checking the oil level prior to commissioning
Check the oil level before commissioning. Correct the oil quantity when required. Please
observe Checking and changing lubricants (Page 60).
Siemens AG recommends a complete oil change after a storage time longer than 24 months:
•
For gearboxes with long-term preservation.
•
For gearboxes supplied completely filled with oil.
Please observe Checking and changing lubricants (Page 60).
Summary of Contents for SIMOGEAR 2KJ40
Page 1: ......
Page 2: ......
Page 8: ...Table of contents BA 2030 2KJ4 6 Operating Instructions 07 2020 A5E50009094A RS AL ...
Page 58: ...Operation BA 2030 2KJ4 56 Operating Instructions 07 2020 A5E50009094A RS AL ...
Page 82: ...Disposal BA 2030 2KJ4 80 Operating Instructions 07 2020 A5E50009094A RS AL ...
Page 148: ......