Configuring
You configure the following:
● Bus link on PROFIBUS DP
During configuration, the couplers for the FF segment are always part of the bus link.
● FF devices on FF segment (FF subsystem in HW Config)
The necessary configuration steps are described in section "How to prepare a FOUNDATION
Fieldbus for FF devices (Page 27)".
S7-400H as DP master
The following AS components operate as DP master:
● CP 443-5 ext.
● PROFIBUS DP connection of the CPU
The following requirements are met for the DP master systems:
● The DP masters process the same user program.
● The DP masters have the same parameter assignment and configuration for the interface
modules.
Additional information
● You can find more information on redundant design of the PROFIBUS PA in the
documentation
SIMATIC; Process Control System PCS 7; Fault-Tolerant Process Control
Systems chapter "Redundant PROFIBUS PA".
● You can find information on the hardware design of the FOUNDATION Fieldbus in the
following documentation:
– Operating Instructions
SIMATIC; Bus Link; FF Link
– Operating Instructions
SIMATIC; Bus Link; Compact FF Link
● Information regarding the configuration of the redundant fieldbus with AFD/AFS can be
found in the following documentation:
SIMATIC; Bus Links; DP/PA Coupler, Active Field Distributors, DP/PA-Link and Y-Link
7.2
System changes during operation
The following changes are possible:
● Changing the DP master system
● Changing parameters in FF devices
● Inserting or removing entire FF segments
● Inserting or removing FF devices
Observe the rules for modifying the system during operation using CiR.
Redundancy and system changes during operation
7.2 System changes during operation
FOUNDATION Fieldbus
68
Commissioning Manual, 02/2015, A5E32711026-AC