Engineering
5
Overview
You configure the FOUNDATION Fieldbus and create the FF devices in HW Config.
You configure a bus link suitable for the connection of an FF segment on the PROFIBUS DP .
A "Foundation Fieldbus: FF subsystem" object with standard bus parameters is created
automatically with the bus link.
You assign the parameters of the FF devices with SIMATIC PDM.
Basic procedure
If you want to connect an FF device to an automation system in a PCS 7 project, the following
steps are required:
1. Integrating device descriptions (Page 26)
2. Create a bus link with FOUNDATION Fieldbus (FF subsystem) on the DP master system
– Insert an FF device and assign the address on the FF segment
– Assign addresses in the I/O range and symbolic names for signals
– Specify the device name and object properties
4. How to configure FF-internal interconnections (Control in the field) (Page 35)
5. Configure the bus parameters (Page 47)
6. Generate a schedule and load it into the FF segment (Page 60)
Details about the individual steps are given in the following sections.
See also
How to replace an FF device (Page 39)
How to assign parameters of the FF devices (Page 40)
“Interconnection Editor" dialog box (Page 37)
FOUNDATION Fieldbus
Commissioning Manual, 02/2015, A5E32711026-AC