Commissioning
Initializing the detector
6
75
Building Technologies
007016_i_en_--
Fire Safety
2012-09-07
6.9
Initializing the detector
After the fine-tuning of the detector optics, the detector must be initialized with the
hood screwed on.
1
2
3
Initializing the detector
1 End plug
3 Button
2 Connection sockets
The detector line is switched on.
Setting of the detector optics is complete.
1. Remove the sealing plug (1) from the hood.
2. Connect the MC link cable to the connection socket (2) of the detector.
The standardized signal value and the detection distance are displayed in
the 'Adjust' menu on the adjustment device. Example:
1133
50m
Adjust
FDL241-9; commissioning & adjustment data
(values displayed on adjustment device)
distance
[m]
deviate-
signal
[%]
covered-
reflector
value
[%]
values
date &
action
signal-
value
[-]
50 1133
3. Copy the two display values onto the two labels.