Commissioning
Commissioning on a collective detector line
6
52 | 66
Building Technologies
007011_m_en_--
Fire Safety
2018-06-28
6.2 Commissioning on a collective detector line
Sequence
1. Set parameter set [ 52]
2. Install flame detector on base for flame detector [ 53]
3. Run performance check [ 54]
You will find information on the individual steps in the specified chapters.
6.2.1 Set parameter set
For collective operation, the parameter set is set via the DIP switches in the flame
detector.
Procedure
w
The parameter set is determined according to the details provided in the
'Planning [ 27]' chapter.
1. Loosen screw (3) on rear of flame detector.
2. Open swiveling cover (1).
3. Use DIP switches (2) to set the parameter set you want (see table below).
4. Close swiveling cover (1) and fix with screw (3).
a
The parameter set is set.
Figure 23: Rear of flame detector with open swiveling cover
1 Swiveling cover
3 Screw for fixing swiveling cover
2 DIP switch
1
2
3