28
9-3. Procedures during Operation
(1) Checks after Startup
Make sure that all meters and indicators are in normal status. (Refer to section “5. Equipment”.)
Check that there is no abnormal vibration or noise.
Check that the exhaust gas color is normal. When operation is normal, the exhaust gas should be
colorless or slightly bluish.
< NOTE >
If abnormal, stop using this generator and request the authorized distributor where the generator
was purchased to repair the generator.
(2) Adjustment during Operation
During load operation, check the voltmeter and finely adjust the voltage using the voltage
regulator dial.
Bleeding air from the fuel system when the engine stops due to running out of fuel
This generator is equipped with an automatic air bleeding mechanism. Perform the
following procedures when the engine stops due to running out of fuel to easily bleed
the air from the system.
Add fuel to the generator.
Turn the starter switch to RUN. Air bleeding is completed in approximately 30 sec.
< NOTE >
Turn the throttle switch to IDLING, start the engine and check that the air is completely bled from
the system. If air bleeding is not complete, engine rotation will not be stable. In that case, repeat
the air bleeding operation.
9-4. Stopping Operation
CAUTION : BURNS
Do not touch the engine and surrounding components immediately after
stopping the engine as they are still hot.
Turn the switches and breakers on the load side to OFF.
Turn the three-phase and single-phase breakers on the operation panel to OFF.
Turn the Throttle switch to IDLING.
The engine cools down for approximately three minutes.
Turn the starter switch to STOP.
1
2
1
2
3
4
5
Summary of Contents for DGM60MK
Page 2: ......
Page 46: ...43 13 Generator Circuit Diagram...
Page 47: ...44 14 Engine Electrical Circuit Diagram...
Page 48: ...2011...