Wall Mount Installation - Square Clock
1) Install the single gang box in the wall. Leave at
least 4 inches between the top of the gang box and
ceiling. Confirm that the bottom of the gang box is
level with the floor.
Ceiling
Minimum
3) Detach the housing from the back of the clock.
Do this by inserting a flat-blade screwdriver about
1/8 inch into each of the slot holes until the housing
detaches. You may hear a snapping noise as the
latches disengage.
4) Release the mounting piece from the back of
the housing by sliding it towards the center of the
housing, then pulling it back and away from
the housing.
2) Run power and communication wiring to the
gang box. See the sections of this manual labeled
“Wiring Information” for additional details,
depending on your system.
If you are using a 2-wire system, pull the
YELLOW and GREEN wires out of
the connector.
CHECK YOUR WIRING
The voltage between the white and black wires
should measure 105-126 volts AC in the 115
volt model, 207-253 volts AC in the 230 volt
model, or 21.5-26.5 volts AC in the 24
volt model.
If you are using the 24 volt model, make sure
that the wiring leading to the clock is from an
ISOLATED transformer.