1 2
3 4
6
The Sapling Company, Inc.
1633 Republic Road
Huntingdon Valley, PA 19006
USA
P. (+1) 215.322.6063
F. (+1) 215.322.8498
www.sapling-inc.com
Wall Mount Installation - Round Metal Clock
3) Attach the communication, power,
and grounding wires from your kit to the
communication and power wires in the gang box.
See the Wiring Guide included later in this manual
for additional details.
1) Install the single gang box in the wall. Leave at
least 17 inches between the bottom of the gang
box and ceiling. Confirm that the bottom of the
gang box is level with the floor.
CHECK YOUR WIRING
The voltage between the white and black wires
should measure 105-126 volts AC in the 115
volt model, 207-253 volts AC in the 230 volt
model, or 21.5-26.5 volts AC in the 24
volt model.
If you are using the 24 volt model, make sure
that the wiring leading to the clock is from an
ISOLATED transformer.
2) Run power and communication wiring to the
gang box. See the sections of this manual labeled
“Wiring Information” for additional details,
depending on your system.
If you are using a 2-wire system, pull the
YELLOW and GREEN wires out of
the connector.
4) Use the #6-32x1/2 screws to attach the mounting
bracket to the gang box. The gang box should be at
the bottom of the mounting piece.
17” Minimum
43.2 cm