iDCS 500 Release 2 / OfficeServ
INSTALLATION
TECHNICAL MANUAL
PART 2 MARCH 2004
2.4
provided screws in the dimples in the rear lower panel of the top cabinet. Replace
the rear panel on the top cabinet. A separate single point ground must be
connected to the main cabinet ground bar. Install the ground harness between the
cabinets ground bars prior to installing any cards (
When a power supply is installed, verify that the power switch is in the proper
voltage setting, i.e., 110
Connection, 2.9 MDF Cabling, Part 3, and Part 4 of this manual
basic required configuration and to make the system operational.
2.5 ADDING an iDCS 500 EXPANSION CABINET
WARNING
: Unplug all sources of AC and DC electricity from the system before
attempting this procedure.
1. Unplug the system AC and/or DC power sources.
2. Disconnect all cables and wires from the system.
3. Proceed as instructed in
Part 2.3 Two Cabinet Installation, Part 2.4 three cabinet
installation, or Part 2.6 Rack Mounting a Cabinet.
4. Insert the PSU60B, LCP2 and additional cards in the added cabinet.
5. Connect CIC cable assembly to the LCP2.
6.
Connect the AC/DC power cables to the cabinets.
NOTES:
1.
To activate the new cabinet, the additional card slots must have any new cards
inserted and recognized by the MCP2 processor.
2.
If this is the first expansion cabinet on the system (i.e. you are converting from a
single cabinet to a two cabinet system) then an ESM board is also required. The
ESM is a daughter board that installs on the MCP2 card.
2.6 RACK MOUNTING an iDCS 500 Cabinet
Prepare all of the iDCS 500 cabinets by removing the side and front covers of the
cabinets prior to installation to avoid damaging the covers and to allow access to the
interior. In addition the top covers and the bottom panels from the cabinets must be
removed.
1.
Remove the four screws holding each side cover support bracket and remove
the brackets from both sides of the cabinet
. These brackets are
not required for rack mounting.