Confidential
3
.
Installing the Product
English 8/2019. Rev 0.0
45
3.10.3
Battery Module Installation
1.
Transport battery modules to the installation location.
2.
Measure the modules’ voltage and internal impedance. All modules in one rack frame must be near the same state of charge.
The batteries must have an output within 300mV of each other and internal impedance difference of 1.3mΩ. Refer to Table
3-8: Module Voltage and Internal Impedance.
3.
Place the battery modules on the rack frame.
Important
Samsung recommends installing Battery Modules in the upper shelves first and proceeding to
the bottom.
(Two Type B battery modules are inserted in the ninth shelf from the bottom.)
Sixteen battery modules can be inserted into a rack frame as shown in Figure 3-27.
Refer to 2.1.1 for information on the different battery module types.
Figure 3-25: Insertion of Modules on the Ninth Shelf from the Bottom
Two Type B Battery
Modules
Summary of Contents for 136S
Page 1: ...Confidential English 8 2019 Rev 0 0 LIB System for UPS Installation Manual 136S ...
Page 4: ...Confidential English 8 2019 Rev 0 0 ...
Page 10: ...Important Safety Instructions Confidential vi English 8 2019 Rev 0 0 ...
Page 18: ...Confidential Table of Contents viii English 8 2019 Rev 0 0 ...
Page 153: ...Confidential Memo ...
Page 154: ...Confidential Memo ...
Page 155: ...Confidential Memo ...
Page 156: ...www SamsungSDI com ...