Page 7
Victrix 24kW X Instructions
Flue Systems
Horizontal intake kits—exhaust ø 60 /100
Install the bend with flange (2) on the central hole of the
boiler inserting the seal (1) with the round protrusions
facing downwards in contact with boiler flange and tighten
using the screws supplied with the kit. Fit the smooth male
end of the 60/100 concentric terminal pipe (3) until it reaches
to the stop on the female end of the bend (2), making sure
the internal and external sealing rings are fitted; this will en-
sure the connection is properly sealed. Additional exten-
sions and bends may be installed if required using the same
method.
Ensure that all seals are fitted and that the outer and inner
pipes are installed so that all joints are perfectly sealed.
Ensure that the terminal is installed the right way up.
A lubricant may assist in overcoming the friction of the seals.
Oils and conventional greases are not compatible with the
EPDM seals used and should never be used for this pur-
pose. Silicone sprays are compatible with EPDM and may be used. Please contact RVR for more information.
A supporting clamp should be installed every three meters. The flue system should be slightly inclined so that
any condensate flows towards the boiler. This avoids any drips from the external flue terminal.
The maximum possible overall length after the first bend (2) is 12.9 straight and horizontal meters. See
the section on extended flue design for more information
Vertical kit with aluminium tile ø 60 /100
Install the concentric flange (2) on the central hole of the boiler insert-
ing the seal (1) with the round protrusions facing downwards in con-
tact with boiler flange and tighten using the screws supplied with the
kit.
Fit the male end (smooth) of the adapter (3) in the female end of the
concentric flange (2) until it reaches the stop on the female end of the
flange, making sure the internal and external sealing rings are fitted;
this will ensure the connection is properly sealed. Additional exten-
sions and bends may be installed if required using the same method.
Installing the flashing- Replace tiles with the aluminium sheet (5),
shaping it to ensure that the rainwater runs off. Position the fixed half-
shell (7) on the aluminium tile and insert the intake/exhaust pipe (6).
Fit the male end (6) (smooth) of the 60/100 concentric terminal up to
the stop on the female end of the adapter(3), making sure that the ring
(4) is already fitted; this will ensure hold and joining of the elements
making up the kit.
Ensure that all seals are fitted and that the outer and inner pipes are
installed so that all joints are perfectly sealed. A lubricant may assist in overcoming the friction of the seals. Oils
and conventional greases are not compatible with the EPDM seals used and should never be used for this pur-
pose. Silicone sprays are compatible with EPDM and may be used. Please contact RVR for more information.
NB: If the terminal or extension pipes need shortening ensure that the inner pipe protrudes by 5mm with
respect to the external pipe.
When the boiler is installed on an external wall, the standard horizontal concentric 60/100 flue kit will normally
be used to flue the boiler. This is shown in the diagram.
It is often necessary to install a longer flue system to cater for site conditions. There are several different flue
system sizes available for the Victrix 24kW boiler.