it must not be overloaded (max. 120 kg)! Lifting of persons is
strictly prohibited!
•
Connecting several tablet PCs with a machine is prohibited!
2
Installation instructions
Installation and commissioning of the machine may only be carried
out in the presence of a Rühle service technician or by persons au-
thorised by Rühle.
Rühle GmbH Lebensmitteltechnik accepts no liability for any damage
resulting from failure to comply with these operating instructions.
2.1
Machine transport and setup
Please refer to the short instructions supplied with the machine re-
garding transport and setup of the cutting centre.
The machine and machine parts must be transported by 2
persons (1 person to operate the floor truck/1 person to
supervise transport).
The power supply line must not be damaged by driving
over or crushing it!
The machine must be shut down until a damaged power
supply line has been repaired!
Ensure that the machine is stable!
Foundation load: 7,1 kN/m²!
Set up the machine on a solid level floor with sufficient
load bearing capacity!
2.2
Workplace description
The work area around the machine is at least 0.5 m on all sides; for
maintenance work it is at least 1 m; if used as passage way, it is at