4.4.2 Checklist for returning to service
Checklist for returning to service
1.
ROTEX GSU installed correctly according to an installation version and without recognisable damage?
Yes
2.
Combustion air supply secured?
Yes
3.
Sufficient venting of the heating room in ambient air-dependent operation?
Yes
4.
Does the mains connection conform to the specifications?
Yes
5.
Mains voltage 230 Volt, 50 Hz?
Yes
6.
LAS-flue gas line connected correctly and leak-proof?
Yes
7.
Storage tank topped up with water to overflow, condensate drain line connected correctly and leakproof?
Yes
8.
In restoration applications: Was the heat distribution network cleaned? Is a dirt filter installed in the heating return flow?
Yes
9.
Is a membrane expansion tank fitted according to specifications and of the requisite size?
Yes
10. Is the safety valve connected to a free outlet?
Yes
11. Is the system water pressure in the green range?
Yes
12. Are boiler and heating system vented?
Yes
13. Are all sensors connected and correctly positioned?
Yes
14. Is the mixer group and the mixing circuit sensor (optional) connected correctly to the circuit board?
Yes
15. Is the room control (optional) connected correctly to the circuit board?
Yes
16. Is the gas connection installed according to specifications, expertly and correctly?
Yes
17. Is the gas line vented expertly and leakproof?
Yes
18. Do the gas type and gas inlet pressure correspond to the values indicated on the boiler sticker?
Yes
The system may be returned to service only if the answer to all the questions is "yes".