Start-up
FA ROTEX A1 BGe - 02/2014
23
5.2
Checklists for start-up
Checklist before start-up
1.
Is the ROTEX A1 correctly set up according to an admissible set up variant and without visible damages?
Yes
2.
Combustion air supply secured?
Yes
3.
Adequate ventilation and extraction in the heating room with limited room-air independent (separate flue
gas/intake air) or room-air dependent operation?
Yes
4.
Does the mains connection conform to the specifications?
Yes
5.
Is the mains voltage 230 V, 50 Hz?
Yes
6.
Flue gas line connected correctly with a consistent gradient (at least 3°) and no leaks?
Yes
7.
Condensate box correctly connected, filled with water and leakproof?
Yes
8.
Condensate drain line with consistent gradient and with free discharge connected and no leaks?
Yes
9.
On restoration: Heat distribution network flushed out? Sludge separator fitted in heating return?
Yes
10. Is the diaphragm expansion tank mounted according to specifications and of the requisite size?
Yes
11. Is the safety valve connected to a safe free drain?
Yes
12. Has the quality of the filling water been checked and has any necessary water preparation been carried out?
Yes
13. System water pressure within prescribed range?
Yes
14. Are boiler and heating system vented?
Yes
15. In case of systems with a hot water storage tank:
a) Storage tank filled?
Yes
b) Is the 3-way diverter valve correctly mounted on the flow connection and PCB plug inserted?
Yes
16. Are all sensors connected, correctly positioned and activated?
Yes
17. Mixer group, mixer module and mixer circuit sensor (optional) connected correctly?
Yes
18. Room controller (optional) correctly connected to the controller?
Yes
19. Is the gas connection installed according to regulations, professionally and correctly?
Yes
20. Is the gas line vented expertly and has it been checked for leaks?
Yes
21. Do the gas type and gas inlet pressure correspond to the values indicated on the burner sticker?
Yes
The system may only be started up if all questions can be answered with "Yes".
Checklist after start-up
A
When the heating circulation pump runs, does the heating heat up?
Yes
B
Is the flow pressure for the gas type within the permitted range?
Yes
C
Have the screws for the gas pressure test points been retightened and are they leakproof?
Yes
D
Has the resistance of the flue gas pipe been measured and if so, is the measured resistance higher than the re-
quired minimum resistance?
Yes
E
Have the burner settings been tested using a flue gas analyser and do the values lie within the prescribed range?
Yes
F
Has the sound-deadening hood been refitted after commissioning?
Yes
G
In case of systems with a hot water storage tank: Has the 3-way diverter valve connector been plugged in fol-
lowing start-up?
Yes
The system may only be handed over to the user/owner if all questions can be answered with "Yes".
Ɣ
Fill out the enclosed installation and instruction form as well as the first pages of the operating manual together with the.