Remove the 8 nuts and withdraw the immersion heater. Take care when lifting the immersion heater out of the cylinder and work within
safe working practices.
#
Carefully remove any scale from the surface of the immersion.
CAUTION
DO NOT use a sharp implement as damage to the element surface could be caused.
#
Ensure sealing surfaces are clean and seals are undamaged, if in doubt fit a new gasket. (spare part number 95611025)
#
Replace immersion heater(s) and make sure the 8 nuts are correctly torqued (20Nm or 14.75 ft/lbf)
#
Rewire, check, close and secure immersion heater housing cover(s).
Expansion vessel charge pressure
#
Remove the dust cap on top of the vessel.
#
De-pressurise the system by turning the mains supply off and then opening a hot tap.
#
Check the charge pressure using a tyre pressure gauge. The pressure must be set in accordance with the inlet pressure set on the pressure
reducing valve.
#
If it is lower than the required setting it should be recharged using a tyre pump (Schrader valve type).
CAUTION
DO NOT OVER-
CHARGE
#
Re-check the pressure and when correct replace the dust cap.
Re-commissioning
#
Check all electrical and plumbing connections are secure. Close the drain cock.
#
With a hot tap open, turn on the cold water supply and allow unit to refill.
#
DO NOT switch on the immersion heater(s) or boiler until the unit is full of water.
#
When water flows from the hot tap, allow it to flow for a short while to purge air and flush through any disturbed particles.
#
Close hot tap and then open successive hot taps in system to purge any air.
#
When completely full and purged check system for leaks.
#
The heating source (immersion heater(s) or boiler) can then be switched on.
10. Troubleshooting
Summary of Contents for 1000 Indirect
Page 2: ......
Page 11: ......
Page 13: ...Figure 3 Indirect wiring diagram 1 Thermostat Option 2...
Page 15: ...Figure 4 Single phase wiring schematic...
Page 18: ...2 port zone valve...
Page 19: ......
Page 24: ......
Page 31: ......
Page 35: ...Figure 12 Auxiliary controls...
Page 36: ...Figure 13 Indirect controls page 18 8 Operation 8 1 General...
Page 45: ...3 7 8 Part No See table Part No 95 605 176 9 12 13 Part No See table Part No 95 605 182...
Page 46: ...14 15 Part No 95 607 367 Part No 95 607 425 16 18 19 21 Part No See table Part No See table...
Page 51: ...page 27 page 28 page 29 MAINS PRESSURE HOT WATER STORAGE SYSTEM COMMISSIONING CHECKLIST...
Page 52: ......
Page 54: ......