Grand Bay 40 Direct Vent Freestanding
Page 10
January 2000
BRICK INSTALLATION
The brick in this unit is packed in a separate box to prevent breakage during shipping. To install the
brick, follow the directions below:
1. Place brick A on the lower bottom left side of the firebox at an angle, and tip the top edge up
until it slides into the slots on the top of the firebox and behind the manifold block. Bend brick
retainer tab down.
2. Place brick B on the lower bottom right side of the firebox at an angle, and tip the top edge up
until it slides into the slots on the top of the firebox. Bend brick retainer tab down.
3. Place brick C on the left side of the firebox floor in front of the manifold block.
4. Place brick D on the right side of the firebox floor so that the cutout slides around the log
holder.
5. Slide brick E in front of the front burner tube so that the brick fits between the burner tube and
the face of the insert. Brick must be moved toward face of insert, and MUST NOT BLOCK
front burner tube air shutter.
After left and right brick panels are installed, bend brick
retainer tabs down (as shown below) to insure panels
do not move from their correct locations.
BRICK RETAINER TAB
BRICK
INST
ALLA
TION:
Brick
Retainer
Brick A
Gas
Manifold
Brick C
Gas
Manifold
Brick D
Log
Holder
Front Log
Support
Brick E
Brick
Retainer
Brick B