Installation Site

Please note the following guidelines that apply to the installation site:

• 

Solar modules are not explosion-proof and are not suitable for 
use in explosive environments.

 

Ä

Do not operate solar modules near highly flammable gas and 
vapors (e.g. gas tanks, gas stations).

 

Ä

Do not install modules in enclosed space.

 

Ä

Do not install modules in locations where they may be submerged 
in water (e.g. floodplains).

 

Ä

Do not use modules as a substitute for the normal roofing (e.g. 
modules are not watertight).

 

Ä

Do not install modules in close proximity to air conditioning 
systems.

 

Ä

Do not install modules above 13,120 ft (4,000 m) altitude above 
sea level.

 

Ä

Contact with saline water (e.g. spray water from the sea) and 
salt aggregation on the modules must be avoided.

 

Ä

Do not bring any chemical substance (e.g. oil, solvent etc.) into 
contact with any part of the panel. Only substances, which are 
released by Q CELLS, are allowed to be used during installation, 
operation and maintenance.

 

Ä

Any installation of modules on surfaces of water is prohibited. 
This includes installations on floating as well as pile-based 
platforms. Q CELLS may extend the coverage of its warranty 
to such installations, based on a case by case assessment of 
the system design and location. A prior written consent by the 
warrantor is required in any case.

Prevention of Shadowing Effects

Optimal solar irradiation leads to maximum energy output:

 

Ä

For this reason, install the modules so that they face the sun.

 

Ä

Avoid shadowing (due to objects such as buildings, chimneys 
or trees).

 

Ä

Avoid partial shading (for example through overhead lines, 
dirt, snow).

Limitations

The solar modules are designed for the following applications:

• 

Operating temperatures from –40 °F to +185 °F.

• 

Pull loads and push loads according to chapter „2.3 Mounting 
Options“ 
(‘Test Load’ in accordance with IEC 61215 and ‘Design 
Load ×1.5’ in accordance with UL 61730).

• 

Installation using a mounting structure for solar modules.

Mounting Structure Requirements

Requirements for the mounting structure:

• 

Conform to the necessary structural requirements.

• 

Compliant with local snow and wind loads.

• 

Properly fastened to the ground, the roof, or the façade.

• 

Forces acting on the module are relayed to the mounting sub-
structure.

• 

Ensures sufficient rear ventilation of the module.

• 

Avoid the usage of different metals to prevent contact corrosion.

• 

Allows for stress-free expansion and contraction due to tem-
perature fluctuations.

 

Ä

Ensure that no additional forces are applied through the mounting 
system into the module except for the wind and snow loads. 
Additional forces and moments of torque at the mounting 
positions caused by torsions, displacements or vibrations in 
the mounting system are not allowed.

 

Ä

Ensure that the clamps and the mounting frame are compatible.

Clamp System Recommendations

Use customary clamps that satisfy the following requirements:

• 

Clamp  width:  ≥ 1.5 in  (38 mm).

• 

Clamp height compliant with a 1.38 in (35 mm) frame height.

• 

Clamp depth: 0.2-0.47 in (5-12 mm). (applicable for all CL and TC 
clamping mounting options at section „2.3 Mounting Options“)

• 

Clamps are not in contact with the front glass.

• 

Clamps do not deform the frame.

• 

Clamps that satisfy the structural requirements based on the 
conditions of the installation site according to the applicable 
regulations and technical standards.

• 

Long-term stable clamps that securely affix the module to the 
mounting frame.

Module Orientation Requirements

• 

Vertical or horizontal installation is permitted.

 

Ä

Ensure that rain and melting snow can run off freely. No water 
accumulation.

 

Ä

Ensure that the drainage holes in the frame are not covered. 
No sealing.

75°

 

Ä

Maintain the permissible angle of inclination.

• 

Minimum angle of inclination: 3°

• 

Inclination angles above 75° may be limited by 
local regulations

 

Ä

Standing water on the modules glass needs to be 
avoided. 

2  PLANNING

2.2  REQUIREMENTS

Fig. 2: 

Installation options for crystalline Q CELLS modules. All dimensions are given in inch (mm in brackets). Also observe 
the maximum test loads and clamping range as specified on page 9. 
The illustrated installation options apply for both horizontal and vertical module orientation. 

 

Module 

Clamp 

Subconstruction 

Mounting profile

2  PLANNING

2.3  MOUNTING OPTIONS

TYPE OF
INSTALLATION

POINT MOUNTING SYSTEM

LINEAR MOUNTING SYSTEM

INSTALLATION 
WITH CLAMPS

HYBRID CLAMPING

CL1a

0.79-21.6

(20-550)

CL3

11.8-21.6

(300 - 550)

mCL3

11.8-21.6
(300 - 550)

CL1b

11.8-21.6

(300-550)

≥ 0.59 - 11.2
  (15 - 285)

The module is considered to be in compliance with UL 61730 only when the module is either mounted in the manner specified by 
the mounting instructions, or when the mounting means has been evaluated with this PV module to UL 2703. A module with exposed 
conductive parts is considered to be in compliance with UL 61730 only when it is either electrically grounded in accordance with the 
manufacturer’s instructions and the requirements of the National Electrical Code, ANSI/NFPA 70 (2014-2017), or when the bonding 
means has been evaluated with this module to UL 2703.

0.79 - 3.94
(20 - 100)

CL2a

NA

0.79 - 3.94
(20 - 100)

CL2b

NA

0.79 - 3.94
(20 - 100)

CL5

15.8 - 21.7
(400 - 550)

NA

Summary of Contents for Q.PEAK DUO XL-G10.c

Page 1: ...Valid for North America INSTALLATION AND OPERATION MANUAL Q PEAK DUO XL G10 2 G10 c solar module series...

Page 2: ...are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation and mai...

Page 3: ...ble documents This installation manual is only valid in combination with the following technical information DOCUMENT TYPE Product data sheet Packaging and transport information MISUSE OR INCORRECT US...

Page 4: ...tress free expansion and contraction due to tem perature fluctuations Ensurethatnoadditionalforcesareappliedthroughthemounting system into the module except for the wind and snow loads Additional forc...

Page 5: ...YSTEM INSTALLATION ON MOUNTING POINTS INSTALLATION WITH INSERTION PROFILES NOT PERMITTED TRACKER INSTALLATION ON MOUNTING POINTS TB1a 35 8 908 TB2a 35 8 908 35 8 28 1 17 9 908 713 454 TB1b 28 1 713 TB...

Page 6: ...the module TC1 Ensure minimum support depth of 12mm on the backside and 10mm on the front side of the module FB1 FB2 TB1a TB2a TB1b TB2b mFB2 Use M8 corrosion proof screws and washers diameter 15 8mm...

Page 7: ...ng factor of 125 percent 80 percent derating which might be applicable Please follow the valid national guidelines for the installation of electrical systems refer to section 690 8 of the NEC for an a...

Page 8: ...out the installation alone Only install undamaged modules and components Do not modify the module e g do not drill any additional holes 3 INSTALLATION 3 2 PREPARATION OF INSTALLATION confirmation let...

Page 9: ...Ensure that the modules are disconnected at the inverter prior to separation Be sure to observe the time intervals specified by the inverter manufacturer after switching off the inverter Make sure th...

Page 10: ...ick click DANGER Risk of fatal injury due to electric shock Ensure that all electrical components are in a proper dry and safe condition SOLAR 4 ELECTRICAL CONNECTION 4 3 CONNECTION OF MODULES DANGER...

Page 11: ...and backing nut Care should be taken to avoid the use of grounding hardware of dissimilar metals which may lead to corrosion Option B Integrated grounding methods The Q CELLS modules can be bonded wi...

Page 12: ...ing to the state of the art and taking into account all relevant safety issues and general product properties e g but not restricted to electrical safety mechanical stability load limits depending on...

Page 13: ...ithout notice Q CELLS Installation manual solar modules Q PEAK DUO XL G10 2_G10 c_2022 01_Rev02_NA 24 INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q PEAK DUO XL G10 2 G10 c Q CELLS Free the substru...

Reviews: