DANGER! 
Risk of fatal injury due to electric shock!

When disconnecting an electric circuit carrying direct current, 
electric arcs can occur that may result in life-threatening injuries.

 

Ä

Do NOT unplug the cable when under load.

 

Ä

Do NOT connect any exposed cable ends.

 

Ä

Electrical work may only be performed by qualified and skilled 
personnel (see page 3).

A solar module generates electrical current and voltage even 
at a low intensity of illumination. Sparks and electric arcs may 
result from the separation of a closed circuit. These can result 
in life-threatening injuries. The danger increases when several 
modules are connected in series.

 

Ä

Please be aware of that the entire open circuit voltage is active 
even at low levels of solar irradiation.

 

Ä

Please follow the valid national regulations and safety guidelines 
for the installation of electrical devices and systems.

 

Ä

Please make sure to take all necessary safety precautions. With 
module or phase voltages of more than 120 V, the safety extra-
low voltage range is exceeded.

 

Ä

Carry out work on the inverter and the wiring with extreme 
caution.

 

Ä

Ensure that the modules are disconnected at the inverter prior 
to separation.

 

Ä

Be sure to observe the time intervals specified by the inverter 
manufacturer after switching off the inverter.

 

Ä

Make sure that the plugs can not be connected unintentionally.

 

Ä

Before working on the contacts, check them for safety extra-
low voltage.

DANGER! Risk of fatal injury due to electric shock!

 

Ä

Never open the junction box.

 

Ä

Do not remove bypass diodes.

DANGER! Risk of fatal injury due to electric shock!

 

Ä

Never touch live contacts with bare hands.

 

Ä

Cover connectors by suitable protective caps until 
installation.

DANGER! Risk of fatal injury due to electric shock!

 

Ä

Insulate any exposed cable ends.

 

Ä

Only connect cables with plugs.

DANGER! Risk of fatal injury due to electric shock!

 

Ä

Only use dry, insulated tools for electrical work.

4  ELECTRICAL CONNECTION

4.1  SAFETY

0.39 in (10 mm)

0.2 

in 

(5 

mm)

Option 1:

 

Ä

Fasten the module with 4 clamps in the specified 
clamping range, see Fig. 2, p. 7.

 

Ä

Tighten clamps according to manufacturer’s 
instructions.

 

Ä

Maintain an interval of at least 0.39 in (10 mm) 
between two modules along the short side and 
0.20 in (5 mm) along the long side.

NOTE! Module damage may occur!

 

Ä

Do not subject modules to mechanical tension. 
Max.  torsion  0.12 in / ft  (10 mm/m).

Option 2:

 

Ä

Install the module at the 4 mounting points, 
see Fig. 2, p. 7.

 

Ä

Tighten screws according to manufacturer’s 
instructions.

Option 3:

 

Ä

Install the module using mounting profiles, 
see Fig. 2, p. 7.

3  INSTALLATION

3.3  MODULE INSTALLATION

Summary of Contents for Q.PEAK DUO XL-G10.c

Page 1: ...Valid for North America INSTALLATION AND OPERATION MANUAL Q PEAK DUO XL G10 2 G10 c solar module series...

Page 2: ...are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation and mai...

Page 3: ...ble documents This installation manual is only valid in combination with the following technical information DOCUMENT TYPE Product data sheet Packaging and transport information MISUSE OR INCORRECT US...

Page 4: ...tress free expansion and contraction due to tem perature fluctuations Ensurethatnoadditionalforcesareappliedthroughthemounting system into the module except for the wind and snow loads Additional forc...

Page 5: ...YSTEM INSTALLATION ON MOUNTING POINTS INSTALLATION WITH INSERTION PROFILES NOT PERMITTED TRACKER INSTALLATION ON MOUNTING POINTS TB1a 35 8 908 TB2a 35 8 908 35 8 28 1 17 9 908 713 454 TB1b 28 1 713 TB...

Page 6: ...the module TC1 Ensure minimum support depth of 12mm on the backside and 10mm on the front side of the module FB1 FB2 TB1a TB2a TB1b TB2b mFB2 Use M8 corrosion proof screws and washers diameter 15 8mm...

Page 7: ...ng factor of 125 percent 80 percent derating which might be applicable Please follow the valid national guidelines for the installation of electrical systems refer to section 690 8 of the NEC for an a...

Page 8: ...out the installation alone Only install undamaged modules and components Do not modify the module e g do not drill any additional holes 3 INSTALLATION 3 2 PREPARATION OF INSTALLATION confirmation let...

Page 9: ...Ensure that the modules are disconnected at the inverter prior to separation Be sure to observe the time intervals specified by the inverter manufacturer after switching off the inverter Make sure th...

Page 10: ...ick click DANGER Risk of fatal injury due to electric shock Ensure that all electrical components are in a proper dry and safe condition SOLAR 4 ELECTRICAL CONNECTION 4 3 CONNECTION OF MODULES DANGER...

Page 11: ...and backing nut Care should be taken to avoid the use of grounding hardware of dissimilar metals which may lead to corrosion Option B Integrated grounding methods The Q CELLS modules can be bonded wi...