Pylon Technologies Co., Ltd. Confidential Proprietary
8
3
Installation and Configuration
3.1
Installation Preparation
Safety Requirements
Only those who have finished training and knowledge and fully grasp the power
system personnel may install the system. During installation process, one must
always observe the safety requirements listed below and local safety regulations.
All the circuit under 48V connected to the external power supply system must
meet following criteria defined in IEC60950 SELV Requirements.
If operation of the power system is in cabinet, it must ensure that the power
system is not energized first, at the same time battery device must be turned
off.
Distribution cabling must be reasonable and protective measured to prevent
operation of power equipment from touching these cables. Equipment
installation preparation process shown in Figure 3-1
Figure 3-1 Schematic of Installation Process: