19
INSTALLATION OF CEMENT PAD
Lay out the cement pad as shown. Be sure top surface
is level. Allow 2 days cure time before installing
operator. Bolt pattern must be parallel to the gate.
22"
12"
19"
9"
Fence
5"
13"
A
Gate
Opening
Gate
B
30" Min.
Min. Gate Length = Gate OA +B +30"
C
L
Of Drive Chain
Gate
Bracket
19" X 22"
Cement
Pad
4"
Parallel
To Gate
1/2" Mounting
Hardware
( By Others)
2"
6"
3-1/4"
Electrical
Conduit
INSTALLATION TO PAD
1.
Remove auxiliary shelf from operator frame.
(4) 1/4" HEX
BOLTS
AUX. SHELF
MOUNTING
HOLES
20
2. Using 1/2” hardware (Not Supplied) bolt assembled
unit to the pad, being sure to align operator parallel to
the fence.
NOTE:
Drive sprocket, and rollers must face the
fence.
3. Replace auxiliary shelf in operator and secure position
with 1/4” hardware.
Drive Chain
Cement Pad
22"
19"
36" In Ground Or
As Required
By Local Code
FENCE
Electrical Conduit
Depth As Required
By Local Code
NOTE: Separate Conduit
Should Be Used For
Incoming Power And
Control Wiring.
2" Min.
ATTACHING DRIVE CHAIN
1. Install gate brackets at each end of the gate with U-
bolts provided. Do not fully tighten at this time.
2. Attach a chain take up bolt to one end of the drive
chain using a #41 connecting link.