7-6
PODS 16.48-16000 1940 HEX
Document number: 036285.fm
Revision: B
Commissioning
7.8 Commissioning record
This is a step-by-step commissioning record for easy commissioning of Power-One Supply Systems. Do
not continue if any faults occur during this commissioning. The checkpoints are to be considered as a
minimum for commissioning of the system.
Table 7-2 Commissioning record
Checked
(
D
)
Result
1.
Check that rack is levelled
2.
Check that all breakers are turned to “off”
position and that no rectifiers are mounted in the
subrack(s).
3.
Connect AC, and measure voltage on the
mains input connections in the cabinet, Is to be
230V AC (Measure 230V from phase to N when
400V mains input is used)
L1-N:………..V AC
L2-N:...............V AC
L3-N:...............V AC
4.
Mount rest of the rectifiers
5.
After connection of battery, verify right polarity
by measuring the voltage drop across the battery
breakers (normally not more than 5V DC).
6.
Check float charge, U1, and boost charge,
U2. Is to be adjusted according to the battery
manufacture requirements.
U1:……..V DC
U2:.........V DC
7.
Check temperature compensation. Is to be
adjusted according to the battery manufacture
requirements.
Check temperature read off compare to the room
temperature.
Comp. :…….V/10
o
C
Read off:………
o
C
8.
Check symmetry measurement and set
number of battery strings according to actually
supervised battery strings in the system.
Number: ….
Alarm limit:……
9.
Check alarm transmission by running an
alarm test.
Summary of Contents for PODS 16.48-16000 1940 HEX
Page 4: ...1 2 PODS 16 48 16000 1940 HEX Document number titlepage fm Revision B...
Page 10: ...2 6 PODS 16 48 16000 1940 HEX Document number 039158TOC fm Revision B...
Page 23: ...Safety 5 1 Document number 028580 fm Revision A Safety 5 Safety...
Page 40: ...6 14 PODS 16 48 16000 1940 HEX Document number 039160 fm Revision A Installation guide...
Page 41: ...Commissioning 7 1 Document number 036285 fm Revision A Commissioning 7 Commissioning...
Page 92: ...A 10 PODS 16 48 16000 1940 HEX Document number Appendix A fm Revision B Drawings...
Page 94: ...B 2 PODS 16 48 16000 1940 HEX Document number 039418 fm Revision B Configuration c 000313...
Page 95: ...Configuration c 000313 B 3 Document number 039418 fm Revision B Configuration c 000313...
Page 96: ...B 4 PODS 16 48 16000 1940 HEX Document number 039418 fm Revision B Configuration c 000313...