5.5
LIFTING STEPS
–
QUICK OVERVIEW
Lifting the wall is performed by tilting it over the bottom edge from horizontal position, usually
up to an angle of 80-
85 °, from where the wall is tilted to the vertical position by hand.
( 1 ) Wall horizontal
position
( 2 ) Lifting the Wall using
the Jackie Tool
( 3 ) Lifting tool limit
(80-85
°)
( 4 ) Securing the wall against
overfall (illustration)
( 5 )
Lifting the wall from 85° to 90° by hand
Securing the wall against overfall
Securing the wall against falling back
When lifting the wall manually (necessarily
already secured against falling)
from 85° to
90°,
the Tool is released from working position.
The remaining part of rising joist then rests
on the upper edge of the lifted wall. Therefore,
it
’
s necessary to pay attention to the correct
length of the rising joist.
Figure 3
ATTENTION