WALL RELEASING FROM THE LIFTING TOOL
a.
Before lifting the wall to the final position make sure, that the wall is secured against
flipping over the reverse side, as it is shown in Chapter 5.5 in point (5). Means screw up
the straining beams on the wall to be able to secure it early from falling down
or flipping over.
b.
Before lifting the wall to the final position make sure, that the length of the rising joist
is sufficient and the joist has a necessary overlap, as it is shown at Figure 18.
c.
Get the wall into the
vertical position, eventually check the verticality using the builder’s
level and fix it using the straining beam to the floor or bottom plate.
d.
Check the position of the wall bottom edge at the lower plate, straighten it up and fix
it to the bottom plate.
e.
Now you can release the rising joist from the heel and wall and finally remove the lifting
tool from the rising joist.
!!! ATTENTION !!!
AFTER REMOVING THE HEEL FROM THE GROUND (AND PUT OUT
SCREWS) IS NECESSARY TO REPAIR WATERPROFING AND RADON
INSULATION (IF IT IS HARMED) RESPECTING THE MANUFACTURER
RECOMMENDATIONS.
Figure 18
Figure 19