46
Montage CONE FIT
Installation CONE FIT
Installation Step 5:
Attach a sling chain to the Tire Protection Chain at the tread centre and
lift the wheel into upright position. Secure the wheel with safety chocks
before start of tightening procedure.
Installation Step 6:
Attach the lever hoist to the tension chain (as close as possible to the
locking plate) and to the chain sidewall as shown in the picture 3. Start
to tighten the chain until required tension is achieved. Align the tension
chain rings with a hammer against the direction of pull.
Secure the locking plate back into the tension chain, relieve and remove
lever hoist. Thread the tension chain tail through the oval tension chain
rings and attach the last link of the tension chain with the shackle to the
closest ring of the sidewall.
The CONE FIT installation is now complete.
Notice:
After wheels have been installed onto the machine re-tensioning
will be mandatory (see correct chain tension).
Montageschritt 5:
Eine Anschlagkette an der Reifenschutzkette mittig an der Lauffläche
befestigen, und das Rad in stehende Position heben. Vor dem Beginn
des Spannvorgangs das Rad mit Sicherungsböcken absichern.
Montageschritt 6:
Verbinden Sie den Ratschenzug mit der Spannkette (so nahe wie möglich
an der Schließplatte) und der Kettenseitenwand wie in Abb. 3 gezeigt.
Mit dem Spannen der Kette beginnen, bis die erforderliche Spannung
erreicht ist. Spannkettenringe mit einem Hammer entgegen der
Zugrichtung ausrichten.
Schließplatte in die Spannkette einschieben und Ratschenzug lösen
und entfernen. Das Ende der Spannkette durch die ovalen
Spannkettenringe einfädeln und das letzte Glied der Spannkette mit
einem Schäkel am nächstgelegenen Ring der Seitenwand befestigen.
Die CONE FIT Montage ist nun abgeschlossen.
Hinweis:
Nachdem die Räder auf der Maschine montiert wurden, ist
ein Nachspannen unbedingt erforderlich (siehe korrekte Kettenspannung).