Installing the solar batteries (if present)
In solar configuration, the terminal has two batteries:
a first 12V 27Ah battery located in the maintenance compartment,
a second 12V 42Ah battery located in the power supply module.
- The battery voltage test does not make it possible to determine if only one of
both batteries is discharged.
- Always replace both batteries at the same time by well charged batteries.
Tools required:
none
Installing the first battery:
Open the maintenance door.
Install the first battery on its support.
Connect the solar battery cable to the first battery, minding the polarity.
Stack the following while connecting both lugs (starting from the edge of
the battery): screw/battery lug/tooth lock washer/cable lug/toothed
collar nut.
Stack
Close the maintenance door.