7 - Excavation anchoring
StradaPAL – Installation manual
21/43
Comply with the setting time recommended by the concrete supplier.
Finish the ground (if the ground has a concrete or pavement finish, you need
not wait for the concrete to set).
Screw 4 nuts on the anchoring rods up to 12 mm above the base box.
These 4 nuts, which are used to level the terminal, are called
"lower nuts" in the rest of the procedure.
Base
box
1
2
m
m
D8935
Lower nut