4. Maintenance
3160-A2-GB21-90
February 2001
4-11
Alarms
The DSU/CSU can be attached, either locally or remotely, to an ASCII terminal or
printer to display or print alarm messages. Alarms can also be displayed on a PC
that is using a terminal emulation package.
For standalone DSU/CSUs, you can route these alarms to the MODEM port, the
COM port, or both. For carrier-mounted DSU/CSUs, you can route them to the
COM port or dial them out using an external device.
Each alarm message contains a customer identification to indicate which remote
DSU/CSU is reporting an alarm. For information about customer identification,
refer to
Displaying Unit Identity
in Chapter 3,
Operation
.
Possible alarm messages are as follows:
Continuous Loss Of Signal detected at the
x
Interface
(where
x
is either Network or DTE).
Alarm Cleared. Loss Of Signal condition at the
x
Interface
(where
x
is either Network or DTE).
Continuous Out Of Frame condition detected at the
x
Interface
(where
x
is either Network or DTE).
Alarm Cleared. Out Of Frame condition at the
x
Interface
(where
x
is either Network or DTE).
Alarm Indication Signal received at the
x
Interface
(where
x
is either Network or DTE).
Alarm Cleared. Alarm Indication Signal at the
x
Interface
(where
x
is either Network or DTE).
An Excessive Error Rate has been detected at the Network
Interface
.
Alarm Cleared. An Excessive Error Rate at the Network
Interface
.
Yellow Alarm signal received at the
x
Interface
(where
x
is either Network or DTE).
Alarm Cleared. Yellow Alarm signal at the
x
Interface
(where
x
is either Network or DTE).
Continuous Out Of Frame condition detected at synchronous
data port
n
(where
n
is the port number).
Alarm Cleared. Out Of Frame condition at synchronous data
port
n
(where
n
is the port number).
An Excessive Error Rate has been detected at synchronous
data port
n
(where
n
is the port number).
Alarm Cleared. An Excessive Error Rate at synchronous data
port
n
(where
n
is the port number).
Summary of Contents for 3160-A3
Page 16: ...About This Guide x February 2001 3160 A2 GB21 90...
Page 24: ...1 Introduction 1 8 February 2001 3160 A2 GB21 90...
Page 100: ...3 Operation 3 66 February 2001 3160 A2 GB21 90...
Page 142: ...A Front Panel Menu A 2 February 2001 3160 A2 GB21 90...
Page 198: ...C Configuration Options C 54 February 2001 3160 A2 GB21 90...
Page 246: ...E SNMP MIB Objects E 32 February 2001 3160 A2 GB21 90...
Page 280: ...H Asynchronous Terminal Operation H 24 February 2001 3160 A2 GB21 90...
Page 282: ...I Equipment List I 2 February 2001 3160 A2 GB21 90...