SECTION 3 - CHASSIS & TURNTABLE
3-28
– JLG Lift –
3121659
Assembly
1.
Install new O-ring (1) and piston seal (2) to servo piston
(3). Install piston seal over O-ring.
NOTE:
Installing piston seal stretches it, making it difficult to
install servo piston in its bore. Allow 30 minutes for seal to
relax after installation. To speed up seal relaxation, com-
press seal by installing piston head in servo cavity in end-
cap and let it stand for at least five minutes.
2.
After piston seal has relaxed, lubricate and install servo
piston into housing bore. Align piston with ball socket
facing inside of housing.
COMPRESSED SPRING MAY FLY OUT AND CAUSE SERIOUS INJURY. COMPRESS-
ING BLOCK SPRING REQUIRES ABOUT 80 TO 90 LBF (350 TO 400 N) OF FORCE.
USE A PRESS SUFFICIENT TO MAINTAIN THIS FORCE WITH REASONABLE
EFFORT. ENSURE SPRING IS SECURE BEFORE ATTEMPTING TO INSTALL SPIRAL
RETAINING RING. RELEASE PRESSURE SLOWLY AFTER RETAINING RING IS
INSTALLED.
3.
Install inner block spring washer (4), block spring (5),
and outer washer (6) in cylinder block. Using a press,
compress block spring enough to expose retaining ring
groove. Wind spiral retaining ring (7) into cylinder block.
4.
Turn block over and install retaining ring (8), hold-down
pins (9), and ball guide (10) to cylinder block.
3
2
1
3
1.
O-ring
2.
Piston Seal
3.
Servo Piston
Figure 3-19. Servo Piston
7
6
5
4
8
9
10
12
11
4.
Block Spring Washer
5.
Block Spring
6.
Outer Washer
7.
Spiral Retaining Ring
8.
Retaining Ring
9.
Holddown Pins
10. Ball Guide
11. Piston
12. Slipper Retainer
Figure 3-20. Cylinder Kit Assembly
Summary of Contents for JLG 450AJ
Page 2: ......
Page 32: ...SECTION 1 SPECIFICATIONS 1 18 JLG Lift 3121659 NOTES...
Page 80: ...SECTION 4 BOOM PLATFORM 4 2 JLG Lift 3121659 Figure 4 1 Boom Assembly...
Page 81: ...SECTION 4 BOOM PLATFORM 3121659 JLG Lift 4 3 Figure 4 2 Main Boom Assembly Sheet 1 of 2...
Page 82: ...SECTION 4 BOOM PLATFORM 4 4 JLG Lift 3121659 Figure 4 3 Main Boom Assembly Sheet 2 of 2...
Page 83: ...SECTION 4 BOOM PLATFORM 3121659 JLG Lift 4 5 Figure 4 4 Upper Boom Assembly...
Page 84: ...SECTION 4 BOOM PLATFORM 4 6 JLG Lift 3121659 Figure 4 5 Jib Assembly...
Page 118: ...SECTION 4 BOOM PLATFORM 4 40 JLG Lift 3121659 NOTES...
Page 156: ...SECTION 5 BASIC HYDRAULIC INFORMATION HYDRAULIC SCHEMATICS 5 38 JLG Lift 3121659 NOTES...
Page 164: ...SECTION 6 JLG CONTROL SYSTEM 6 8 JLG Lift 3121659 Figure 6 2 Tilt Sensor Location...
Page 169: ...SECTION 6 JLG CONTROL SYSTEM 3121659 JLG Lift 6 13 Figure 6 7 Analyzer Connecting Points...
Page 181: ...SECTION 6 JLG CONTROL SYSTEM 3121659 JLG Lift 6 25 Figure 6 19 Platform Module Sheet 1 of 2...
Page 182: ...SECTION 6 JLG CONTROL SYSTEM 6 26 JLG Lift 3121659 Figure 6 20 Platform Module Sheet 2 of 2...
Page 224: ...SECTION 6 JLG CONTROL SYSTEM 6 68 JLG Lift 3121659 NOTES...
Page 340: ...SECTION 7 BASIC ELECTRICAL INFORMATION ELECTRICAL SCHEMATICS 7 116 JLG Lift 3121659 NOTES...
Page 341: ......