4.3
Connecting the lift
Follow the sequence of operations given below
1. Connect the hoses provided, which lead out of the control unit with their respective
inputs to the lift
(see paragraphs: Hydraulic, pneumatic, electrical connection)
2. Fill the circuit MASTER/SLAVE and remove air from the same circuit.
(see paragraph: Filling of the circuit Master-Slave)
3. Fix the legs of the lift with the raw plugs at the correct distance and perfectly leveled.
(see paragraphs: Lift position and Anchorage capsule installation)
4. Carry out all due tests before using the lift.
(see paragraph: Check and Checks before use)
The control unit must be positioned so that the operator has a full view over the
lift area
4.4. Connecting the lift’s commands
4.4.1. Hydraulic connections
• Open the control unit door
• Bring the hydraulic hoses from the lift to the control unit, through the hole at the base of
the control unit.
• Join the hoses to the hydraulic blocks respecting the numbering system shown
(see photo)
Summary of Contents for Kar 350
Page 7: ......
Page 8: ...2 4 Loading Conditions...
Page 16: ...LIFT...
Page 17: ...19...
Page 19: ...LABEL 6 LABEL 7 LABEL 8 LABEL 9 LABEL 10...
Page 20: ...LABEL 11 LABEL 12 LABEL 13...
Page 26: ...JOIN THE HOSES RESPECTING THE NUMBERING HOLE FOR THE HOSE...