36”
Section 6: Installation
28
10. Assemble the supplied P-Clip roughly 36” from the grounded plug on the supplied
power cord, then secure the P-Clip to the inside surface of the horizontal strut of the
fountain frame with a #8 Torx screw.
11. Install the ring terminal to the inside vertical strut of the dummy unit with the provided
#8 thread cutting hex screw. Screw into one of the empty flared holes of the strut.
Secure power cord
about 36” from the
plug. Lengthen if
necessary.
NOTE:
Only one of the two power cords from the kits will be used.