- 29 -
NL5258G5/NL5300G5
www.New-Leader.com
(800) 363-1771
314732-AA-B
Header
Insert Installation
INSERT HYDRAULIC REQUIREMENTS
Refer to “Spreader Hydraulic Requirements” for speci
fi
cations required for insert installation.
SPREADER PREPARATION
WARNING
Use only lifting devices that meet or exceed OSHA standard 1910.184. Never exceed
work load limits or lift equipment over people. Empty spreader before lifting. Loads may
shift or fall if improperly supported, causing injury.
1. Remove the Inverted “V”, Hillside Divider and side
boards from the spreader, if so equipped, and set
hardware aside. Replace chain shield hardware from
Hillside Divider and torque to spec.
2. Figure 1 - Disconnect feedgate hydraulic hoses (A).
B
A
B
A
Figure 1
3. Figure 2 - Disconnect Endgate harness at rear
electrical bulkhead. Uncap all necessary receptacles.
BIN 3
BIN 2
BIN 2
BIN 1
Figure 2
Recommended sequence of installation is:
1. Spreader
preparation.
2. Insert
preparation.
3.
Mounting of insert.
4.
Connecting hydraulic hoses.
5.
Installation of hillside divider and conveyor cover.
6. Checking
installation.
7.
Checking for leaks and proper functioning.