Digital/SLT Combination Blade (082U) (Figure 2-25)
- P/N 0911058
The Digital/SLT Combination blade provides 8 digital ports and 2 analog ports. This blade allows for
either a 4COIU analog trunk daughter board or 2BRI daughter board to be installed.
The blade provides:
●
8 digital ports
●
2 analog ports
●
2 status LEDs
Without a MEMDB installed, only 1 082U blade can be installed in the system. With a MEMDB,
multiple 082U blades can be installed in the communications server - however, only one 082U blade
can be installed in a 9.5” base chassis or 1 per 19” chassis (for a maximum of 4 082U blades per
communications server). When connecting this blade, the system uses 8 digital port and 2 analog
ports. The blade consumes 10 logical ports (2 analog, 2 digital) plus any ports used by any attached
daughter board.
2.5.4.1
LED Indications
LED Indication
Operation Status
Operation Status
Live LED
(green)
Busy LED
(red)
On
On
Blade initializing
Flashing
(1 second)
On
Blade assignment refused (system
capacity exceeded or software
version incorrect)
Flashing
(1 second)
Trouble found during self-
diagnostics routine.
Flashing
(100 ms)
On
Normal operation
At least 1 channel busy
Off
All channels idle
Off
On
Blocked blade
At least 1 channel busy
Off
All channels idle
Flashing
(80 ms on/
off x 3/400
ms off)
Downloading firmware
●
Blades with “IP3NE” included as part of the blade name printed on the card
cannot be combined with any “IP3WW” version blades. The “IP3NE” are U.S.
versions, while the “IP3WW” are international versions of the blades.
Summary of Contents for UX5000
Page 12: ...x Table of Contents Table of Contents...
Page 18: ...1 6 Chapter 1 Chapter 1 Installing the Chassis...
Page 26: ...1 14 Chapter 1 Chapter 1 Installing the Chassis...
Page 84: ...1 72 Chapter 1 Chapter 1 Installing the Chassis...
Page 90: ...2 4 Chapter 2 Chapter 2 Blade Installation and Startup...
Page 98: ...2 12 Chapter 2 Chapter 2 Blade Installation and Startup...
Page 113: ...Chapter 2 Blade Installation and Startup Chapter 2 2 27 Figure 2 11 EXIFU CABLING...
Page 144: ...2 58 Chapter 2 Chapter 2 Blade Installation and Startup...
Page 172: ...2 86 Chapter 2 Chapter 2 Blade Installation and Startup...
Page 174: ...2 88 Chapter 2 Chapter 2 Blade Installation and Startup...
Page 208: ...4 14 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 212: ...4 18 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 220: ...4 26 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 222: ...4 28 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 224: ...4 30 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 226: ...4 32 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 228: ...4 34 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 254: ...4 60 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 260: ...4 66 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 274: ...4 80 Chapter 4 Chapter 4 Terminals and Optional Equipment...
Page 284: ...5 4 Chapter 5 Chapter 5 LAN Connection...
Page 332: ...vi Index Index...