CHAPTER 3 NDA-24219
Page 24
Revision 2.0
2. PROCEDURE
This section explains the procedures for installing the PBX system. The installer should follow the flowchart proce-
dure shown in
. In the flowchart, an NAP (NEC Action Procedure) Number, denoted on the right side of
each action, refers to the details for each procedure.
Figure 3-2 Procedure Flowchart
START
UNPACKING
MARKING AND DRILLING
INSTALLATION OF
CONNECTION OF
TERMINATION OF
CABLES ON MDF
CABLE RUNNING
TO MDF
SWITCH SETTING OF
MAIN EQUIPMENT
BATTERY
CIRCUIT CARDS
A
PWR CA-A AND
BUS CABLE CONNECTION