6 Commissioning the on-load tap-changer at the transformer manufacturer's site
Maschinenfabrik Reinhausen GmbH 2015
163
4427410/00 EN
OILTAP® R
Commissioning the on-load tap-changer at the
transformer manufacturer's site
Perform the following work and functional checks before commissioning the
transformer.
Bleeding on-load tap-changer head and suction pipe
Before first commissioning, the on-load tap-changer head and the suction
pipe on pipe connection S must be bled.
Bleeding on-load tap-changer head
1.
Open all forward and return valves in the pipe system.
2.
Remove screw cap on air-vent valve E1 on the on-load tap-changer
head cover.
Figure 210: Screw cap
3.
Use screwdriver to lift valve tappet on air-vent valve E1 and bleed on-
load tap-changer head.
Figure 211: Valve tappet
4.
Seal air-vent valve E1 with screw cap (tightening torque 10 Nm).