Furnace Weights 

Heat Only Models –152 lbs (68.95 kg) 
A/C Ready Models -175 lbs (79.38 kg) 

 
 
 
 
 
 
 
 
 

 

 
 
 
 
 
 
 
 
 
 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

 
 
 
 
 

 

 
 
 
 
 
 
 
 
 
 

 

SECTION II: GENERAL INFORMATION 

 

INSPECTION 

As soon as the furnace is received, it should be inspected for 
possible damage during transit. If damage is evident, the extent 
of the damage should be noted on the carrier’s freight bill. A 
separate request for inspection by the carrier’s agent should be 
made in writing. Also, before installation the furnace should be 

This product must be installed in strict compliance with the 
installation instructions and any applicable local, state, and 
national codes including, but not limited to building, 
electrical, and mechanical codes. 

This furnace area must never be used as a broom closet or 
for any other storage purposes, as a fire hazard may be 
created. Never store items such as the following on, near or 
in contact with the furnace. 

1.

 

Spray or aerosol cans, rags, brooms, dust mops, 
vacuum cleaners, or other cleaning tools. 

2.

 

Soap powders, bleaches, waxes, or other cleaning 
compounds. 

3.

 

Plastic items or containers 

4.

 

Gasoline, kerosene, cigarette lighter fluid, dry cleaning 
fluids, or other volatile fluids. 

5.

 

Paper bags, boxes, or other paper products. 

1.

 

Turn off all gas lines before installing appliance. 

2.

 

When leak testing the gas piping system; the appliance 

gas control valve must be isolated from pressures 
exceeding 14 inwc (1/2 psia) (3.5 kPa). 

3.

 

Check the gas inlet pressure before the gas control valve 

to insure the pressure is: 

a.

 

7 inwc (1.744 kPa) for natural gas. 

b.

 

11 inwc (2.74 kPa) for propane gas 

4.

 

Purging of air from gas supply line should be performed 

as described in ANSI Z223.1 - latest edition “National 
Fuel Gas Code”, or in Canada in CAN/CGA-B149.1 or 
B149.2 codes. 

5.

 

Do not attempt to reuse any mechanical or electronic 

ignition controllers which have been wet. Replace 
defective controller.  

6.

 

Servicing or repairing of this equipment must be 

performed by a qualified service agency. 

7.

Do not install unit outdoors.

HAZARD OF ASPHYXIATION:

 Negative pressure 

inside the closet with closet door closed and the 
furnace blower operating cannot be more negative 
than minus 0.05 inwc. 

Any attempt to relocate or bypass a safety control or 
replace safety controls with a control that is not 
approved or incompatible may result in personal injury, 
substantial property damage or death. 

IMPORTANT

1.

 

To prevent premature heat exchanger failure, do 
not locate any gas-fired appliances in area where 
corrosive vapors are present in the atmosphere. 
Refer to Section I COMBUSTION AIR 

DO NOT

 wet electronic components or wire 

connections during the leak test. Wetting electronic 
components may damage to the circuitry and corrode 
the wire connections which can cause a hazardous 
situation. 
Dry any moisture from all leads and terminals if 
wetting occurs. Wait at least 12 hours for the electronic 
components and wire connections to fully dry before 
energizing the system

Because of the potential of odorant fade, a gas leak may not 
be detected by smell. It is recommended that black iron pipe 
be used from the gas valve to outside the home in order to 
prevent gas leaks inside or under the home. Copper tubing 
and brass fittings (except tin lined) shall not be used if the 
gas contains more than a trace (0.3 grains per 100 cubic ft.) 
of hydrogen sulfide gas. Check with your gas supplier about 
gas content and for a gas leak detector. 

Summary of Contents for G18D SERIES

Page 1: ...30 Reading the Inlet Supply Gas Pressure INP 29 14 Separate T stat furnace Cooling Unit Trans W D 17 31 Reading the Outlet Manifold Gas Pressure 29 15 Same T stat Separate Furnace Cooling Unit Trans W...

Page 2: ...enting system Verify the furnace is operating according to the manufacturer s instructions 11 When installed in a Manufactured Mobile Home The combustion air shall not be supplied from occupied spaces...

Page 3: ...he voltage exceeds 132 VAC This furnace must be installed so the components are protected from water Installing and servicing heating equipment can be hazardous due to the electrical and gas fired com...

Page 4: ...btain the model and serial numbers so the correct parts can be ordered The furnace supply air blower is designed for correct performance with this furnace Do not attempt alter or use a different type...

Page 5: ...rom gas supply line should be performed as described in ANSI Z223 1 latest edition National Fuel Gas Code or in Canada in CAN CGA B149 1 or B149 2 codes 5 Do not attempt to reuse any mechanical or ele...

Page 6: ...OR ACCESS Ample clearances should be provided to permit easy access to the appliance The following minimum clearances are recommended 1 Twenty four 24 inches 61 cm between the front of the furnace and...

Page 7: ...hat the requirements of this subdivision cannot be met at the time of completion of the installation the owner shall have thirty 30 days to comply with the above 48 requirements provided that during t...

Page 8: ...mper is full heating or full cooling position Figure 2 Duct Connector Dimensions Floor Base Installation and Duct Connection Downflow combustible floor base is used for installations on combustible ma...

Page 9: ...g the furnace be sure you have enough clearance to install the furnace and clearance for the return air Refer to Table 1 CLEARANCES 2 Remove the top shipping cover and corner posts 3 Remove the upper...

Page 10: ...d velocity of 300 feet per minute 91 44 m minute cannot be used on the furnace return air louvered door because the air velocity is too high and will destroy the filter The filter velocity with this f...

Page 11: ...2 1 27 cm Table 4 allows for a 0 3 W C 0 075 kPa pressure drop in the ON OFF Pressure Convertable OUT P IN P VENT Manifold Pressure Tap Electrical Terminals Gas Supply Line Pressure Tap GAS FLOW Switc...

Page 12: ...natural gas orifice into the bag and hang it on the gas valve 11 Place the gas valve mounting bracket on the burner mounting plate and secure with the screws you removed in step 5 12 Reconnect the el...

Page 13: ...48 72AG 081 0 081 46 72AG 082 0 082 45 72AG 089 0 089 43 10 000 72AG 073 0 073 49 72AG 078 0 078 47 72AG 081 0 082 46 72AG 089 0 089 43 60 00 BTU FURNACE 70 00 BTU FURNACE 77 00 BTU FURNACE 90 00 BTU...

Page 14: ...ized Proper methods for field installing electrical wiring i Between the furnace and devices not attached to the furnace ii Between the separate devices that are field installed and located iii Exteri...

Page 15: ...Current 60 HZ 0 49 0 49 0 49 0 49 Total Unit Amps 2 54 2 54 2 54 2 54 Model G18D060CA3BA G18D070CA3BA G18D077CA3BA G18D090CA3BA Blower Motor HP 1 3 1 3 1 3 1 3 Blower Mortor SPD 5 5 5 5 Blower Motor...

Page 16: ...e routed through side of furnace and connect to the pig tail wires located above the control box The thermostat wires should also be no smaller than 22 gauges Refer to Table 9 for recommended wire gau...

Page 17: ...use located on the left side of the control board that protects the 24 VAC circuit Replace the fuse only with the equivalent 3 Amp Automotive type fuse Separate Heating and Cooling Thermostats If the...

Page 18: ...ypical Single Stage Heating Cooling Digital Thermostat with Two Stage Furnace Figure 19 Typical Two Stage Heating Cooling Digital Thermostat Connections Typical Heat Pump Heating Cooling Thermostat Wi...

Page 19: ...not less than 17 percent The combustion system is fan assisted This Category I direct vent furnace is designed for Manufactured Home and Modular Home applications It may be installed without modifica...

Page 20: ...rews or rivets Figure 20 Roof Jack Mounting Collars Top of Furnace VENTING INTO AN EXISTING ROOF JACK The furnace shall not be connected to another manufacturers factory built roof jack vent system If...

Page 21: ...per installation of the roof jack requires that openings in the roof and ceiling be on the same vertical center line as the furnace flue collar 2 Once the hole has been cut into the roof insert the ro...

Page 22: ...1000 BTU hr The calculation would be the 50 cubic ft per 1000 BTU hr by the 80 000 BTU Input of all appliances 50 x 80 4000 ft 7 Determine ratio of the available volume to the required volume 2400 ft...

Page 23: ...ply with local codes and requirements NOTE The Roof Jack venting system is considered a special venting system Important Consideration must be given for degradation of building materials by flue gases...

Page 24: ...window or door that may be opened 12 inches 30 cm for models 100 000 BTUH 30 kW 36 inches 91 cm for models 100 000 BTUH 30 kW 4 Feet 1 22 m C Clearance to permanently closed window 12 inches 30 cm 12...

Page 25: ...enting systems are permitted and must be installed in accordance with the National Fuel Gas Code ANSI Z223 1 NFPA 54 and or the CSA B149 1 Natural Gas and Propane Installation Codes local codes and th...

Page 26: ...T C ADJUSTIBLE HEIGHT 90 RJF1729 AL 17 29 FLAT 73 85 94 5 106 5 90 RJF2551 AL 25 51 FLAT 81 107 102 5 128 5 90 RJS1729 AL 17 29 3 12 73 85 94 5 106 5 90 RJS2551 AL 25 51 3 12 81 107 102 5 128 5 90 RJS...

Page 27: ...liance connected to the venting system being placed into operation while all other appliances connected to the venting system are not in operation 1 Seal any unused openings in the venting system 2 In...

Page 28: ...for a CU FT Gas Meter The formula for the input calculation of the appliance if you re heating value is in Mj m you using a cubic meter gas meter Example calculating the input for an appliance operati...

Page 29: ...the gas valve Follow the procedure to shut off the furnace located in the Users Information Manual 5 Turn the switch on the gas valve to the OFF position 6 Turn off the gas supply at the ball valve o...

Page 30: ...als HEAT 120 VAC Blower speed tap connection for heating speed COOL 120 VAC Blower speed tap connection for cooling speed XFMR 120 VAC connection to the transformer L1 120 VAC incoming power supply to...

Page 31: ...try If flame is not established on the first trial for ignition period the gas valve is de energized and the inducer remains energized for an inter purge period of 25 seconds The ignitor is then re e...

Page 32: ...ndoor blower motor on heat speed the other outputs will be kept off and the control will display a LED fault code of 5 When flame is no longer sensed the induced draft motor will run through post purg...

Page 33: ...t be per the following A National Electrical Code NEC and or B Canadian Electrical Code CEC and or C State County Local Regional or City Codes 2 If any origional Factory wire must be replaced then rep...

Page 34: ...ys are integrated into the control board Notes 1 All field wiring must be per the following A National Electrical Code NEC and or B Canadian Electrical Code CEC and or C State County Local Regional or...