Installation Steps:
1.
Install the control and evaluation computer (PC) according to the docu-
ments of the manufacturer.
2.
Plug the tube socket (10) of the RADAR antenna over the attachment
pole and clamp it with the M10 fixing bolt.
3.
Check the vertical alignment of the antenna with the built in bubble level
(see Figure 8)
Figure 8: Vertical alignment of the radar beam
4.
Attach a ground wire to the fixing bolt for lightning protection.
5.
Connect cable (7) between RCPD and Junction Box after mounting of the
antenna.
6.
Connect cable (5) to that serial interface of the computer, which was se-
lected in the operating system for the connection of the MRR-2. If this se-
rial port is unknown, it can be looked up in the administration of the "ser-
vices" in the operating system of the computer and it can be changed ac-
cordingly there. See also installation of the control program page 18 ff.
7.
Connect cable (6) of the Junction Box to the mains voltage of 230 VAC
(cable (6)).
8.
Establish the communication between the control program „MRR-2 Con-
trol” and the RCPD-firmware.
9.
Check the correct data transmission and recording.
Ground wire