To fill the tank:
1. Open the tank lid.
2. Use a shovel or a ladle to fill the tank with adhesive. Do not fill the tank
above the loading opening level. The lid must be able to close normally.
Warning
: Risk of burns. Always refill using protective gloves and glasses.
3. Close the lid when you have finished refilling the tank. Different
adhesive types can damage the melting equipment.
Model
Capacity
Macro 200
200 L
200 kg
For a density of 1g/cc
Starting up the melter equipment
Before starting up the melter equipment, it is necessary to check to see if
the unit has been correctly installed and all its input/output and accessory
connections are correctly established.
It is also necessary to make sure that the equipment has been filled with
adhesive and that the operational parameters have been programmed.
To start:
1. Connect the melter’s switch.
If the control card was turned off the last time the machine was disconnected,
it will remain turned off when the machine is started up again (time display).
If the control card was on the last time that the machine was disconnected, it
will turn on when the machine is started up again.
2. Press the ON/OFF button on the control card to turn it on, if it is not
already activated.
By default, the set point and real temperature values shown are those
corresponding to the tank.
The tank (and distributors, hoses and applicators connected) heating control
LED (green) will light up and the tank will begin to heat.
Once it has reached 3° below the programmed temperature (set point) of
the tank, a programmable delay timer starts until, guaranteeing fusion, the
pump receives permission to operate and the signal will be sent to the main
machine, indicated by the two corresponding (green) LEDs.
While the system is running the delay timer both LEDs remains blinking until
the programmed time value has been reached. If then, any other element has
not reached 3° below its temperature setting point, the LEDs turn off.
5 7
5 7
0 7
0 7
1 5 7
1 5 7
1 6 0
1 6 0
Summary of Contents for MACRO 200
Page 1: ...ADHESIVE MELTER MACRO 200 INSTRUCTIONS MANUAL MA 5068 ENG 221220 GLUING SOLUTIONS ...
Page 8: ...FOCKE MELER GLUING SOLUTIONS TABLE OF CONTENTS This page is intentionally left blank ...
Page 32: ...FOCKE MELER GLUING SOLUTIONS INSTALLATION 3 12 This page is intentionally left blank ...
Page 66: ...FOCKE MELER GLUING SOLUTIONS 5 8 MAINTENANCE This page is intentionally left blank ...
Page 71: ...ELECTRICAL DRAWINGS 7 1 MA 5068 ENG MACRO 200 INSTRUCTIONS MANUAL 7 ELECTRICAL DRAWINGS ...
Page 72: ...FOCKE MELER GLUING SOLUTIONS 7 2 ELECTRICAL DRAWINGS This page is intentionally left blank ...
Page 74: ...FOCKE MELER GLUING SOLUTIONS 8 2 PNEUMATIC DIAGRAM This page is intentionally left blank ...
Page 82: ...FOCKE MELER GLUING SOLUTIONS 9 8 SPARE PARTS LIST This page is intentionally left blank ...