4.
With voltage control set for 15 kV output, set stabilizer to
"IN". Voltage should drop to about 13.5 kV.
5.
Follow the shutdown procedure given in Section 8.
6.
Connect the high voltage output to ground.
7.
Set the voltmeter range to 7.5 kV and the megohmmeter
range to X1, stabilizer "OUT".
8.
Operate the set and very carefully turn up the voltage
control.
Note that the megohmmeter moves to full deflection.
9.
After reaching full scale on the X1 megohm range,
advance the voltage control to 25: either or both circuit
breakers must trip in 20 seconds or less with a supply
voltage of 117 volts or more. If the supply voltage is
between 105 and 117 the time for tripping may be as long
as 40 seconds.
10.
Shut down as described in Section 8.
Summary of Contents for ATEC 210415 Series
Page 2: ...15 kV Megohmmeter Test Set Catalog No 210415 Series M...
Page 9: ...M 2 AVTM21 415Ja Rev A June 2005 Figure 1 15 kV Megohmmeter Test Set Catalog No 210415...
Page 13: ...M 6 AVTM21 415Ja Rev A June 2005 M...
Page 19: ...M 12 AVTM21 415Ja Rev A June 2005 M...
Page 23: ...M 16 AVTM21 415Ja Rev A June 2005 Figure 2 Schematic Diagram of the 15 kV Megohmmeter...
Page 30: ...SETTING UP 23 AVTM21 415Ja Rev A June 2005 Figure 4 Testing in a Substation...
Page 32: ...SETTING UP 25 AVTM21 415Ja Rev A June 2005 Figure 6 Testing Transformer Terminals...
Page 33: ...M 26 AVTM21 415Ja Rev A June 2005 Figure 7 DC Motor Test Setup Figure 8 Generator Test Setup...
Page 47: ...M 40 AVTM21 415Ja Rev A June 2005 M...
Page 53: ...M 46 AVTM21 415Ja Rev A June 2005 M...
Page 57: ...M 50 AVTM21 415Ja Rev A June 2005 M...
Page 73: ...M 66 AVTM21 415Ja Rev A June 2005 Figure 15A Interior View Figure 15B Interior View...
Page 75: ...M 68 AVTM21 415Ja Rev A June 2005 M...
Page 81: ...M 74 AVTM21 415Ja Rev A June 2005 M...
Page 82: ...M 2621 Van Buren Avenue Norristown PA 19403 1 800 723 2861 ext 8578 megger com...