42
AGR 070A through 100A
IOMM AGR-1
System Adjustment
To maintain peak performance at full load operation, the system superheat and liquid subcooling may
require adjustment. Read the following subsections closely to determine if adjustment is required.
Liquid Sightglass and Moisture Indicator
The moisture indicator color is an indication of the dryness of the system and is extremely important
when the system has been serviced. Immediately after the system has been opened for service, the
element may indicate a wet condition. It is recommended that the unit operate for about 12 hours to
allow the system to reach equilibrium before deciding if the system requires a change of drier cores.
Bubbles in the sightglass to expansion valve at constant full load conditions indicates a shortage of
refrigerant, a plugged filter-drier, or a restriction in the liquid line. However, it is not unusual to see
bubbles in the sightglass during changing load conditions.
Refrigerant Charging
Liquid line subcooling at the liquid shut-off valve should be between 15° and 20°F at full load. If the
unit is at steady full load operation and bubbles appear in the sightglass, check liquid subcooling.
Thermostatic Expansion Valve
The expansion valve performs one specific function. It keeps the evaporator supplied with the proper
amount of refrigerant to satisfy the load conditions.
The sensing bulb of the expansion valve is installed in the closest straight run of suction line from the
evaporator. The bulb is held on by clamps around the suction line and is insulated to reduce the effect
of surrounding ambient temperatures. In case the bulb must be removed, simply slit the insulation on
each side of the bulb, remove the clamps and then remove the capillary tubing that runs along the
suction line from the valve.
The power element is removable from the valve body without removing the valve from the line.
Superheat and Subcooling
For optimum operation, set the evaporator superheat for 8 to 12°F (4.4 to 6.6°C) and condenser
subcooling (at the liquid shutoff valves) to 15°F to 20°F (8.3°C to 11.11°C).
CAUTION
Before adjusting superheat, check that unit charge is correct and liquid line sightglass is
full with no bubbles.
The suction superheat for the suction leaving the evaporator is set at the factory for 8° to 12°F at full
load. To have full rated unit performance the superheat must be about 8°F at 95°F outdoor ambient.
Crankcase Heaters
The reciprocating compressors are equipped with compressor crankcase heaters located at the oil
sump level. The function of the heater is to keep the temperature in the crankcase high enough to
prevent refrigerant from migrating to the crankcase and condensing in the oil during off-cycle.
Power must be supplied to the heaters 24 hours before starting the compressors.
Water Cooler
The water cooler is of the direct expansion type with removable internally finned tubes. The copper
tubes are individually rolled into heavy duty steel tube sheets and sealed by a steel refrigerant head.
The water connection nozzles which enter and leave the shell are on the same side of the unit. No
special attention is required for the cooler except that clean, filtered water should be supplied.
Summary of Contents for AGR 070AS
Page 20: ...20 AGR 070A through 100A IOMM AGR 1 Figure 9 Typical Field Wiring with Global UNT Controller...
Page 22: ...22 AGR 070A through 100A IOMM AGR 1 Figure 11 Standard Single Point Connection with FanTrol...
Page 24: ...24 AGR 070A through 100A IOMM AGR 1 Figure 13 Unit Control Schematic 2 compressor UNT...
Page 25: ...IOMM AGR 1 AGR 070A through 100A 25 Figure 14 Staging Schematic 2 compressor 4 stage UNT...
Page 26: ...26 AGR 070A through 100A IOMM AGR 1 Figure 15 Staging Schematic 2 compressor 6 stage UNT...
Page 27: ...IOMM AGR 1 AGR 070A through 100A 27 Figure 16 MicroTech Controller Schematic...
Page 28: ...28 AGR 070A through 100A IOMM AGR 1 Figure 17 Unit Control Schematic MicroTech...
Page 29: ...IOMM AGR 1 AGR 070A through 100A 29 Figure 18 Staging Schematic 4 stage MicroTech...
Page 30: ...30 AGR 070A through 100A IOMM AGR 1 Figure 19 Staging Schematic 6 stage MicroTech...
Page 31: ...IOMM AGR 1 AGR 070A through 100A 31 Figure 20 Unit Control Schematic 2 compressor MicroTech...
Page 32: ...32 AGR 070A through 100A IOMM AGR 1 Figure 21 UNT Instrument Layout See legend on page 34...
Page 35: ...IOMM AGR 1 AGR 070A through 100A 35 Figure 25 MicroTech Sensor Layout...
Page 99: ...IOMM AGR 1 AGR 070A through 100A 99 Notes...
Page 100: ...Post Office Box 2510 Staunton Virginia 24402 USA 800 432 1342 www mcquay com...