Trans
– the transmission %, described in Chapter 2.
.
Obs
– a % measure of the amount of laser light obscured by the spray.
When no spray is present the obscuration is 0%. The value increases as the
spray concentration increases. It is equivalent to 100-
Trans
, for example
95% transmission
º
5% obscuration.
.
Cv
– the volume concentration. This is calculated in volume (%) from the
Beer-Lambert law and is expressed in Parts Per Million (PPM).
.
SSA
– Specific Surface Area, the total area of the particles divided by the to-
tal weight. If using this value, it is important that the density of the spray is
defined (on the first
Analysis
SOP dialogue). This figure is a mathematical
calculation based on the assumption that the particles are both spherical and
non-porous.
.
%>x1
,
%<x1
– percentages above or below a particle size.
.
x1 < %< x2
– the percentage between two particle sizes.
.
[Dv(x1) - Dv(x2)]/Dv50 –
this measures the width of the distribution.
The final parameter is always the
Dv(50)
and
x1
should be greater than
x2
.
When
x1
=90 and
x2
=10 the value is called the
span
. The narrower the
distribution, the smaller the span becomes. The
span
is calculated as:
Dv(90)
Dv(50)
-
Dv
( )
10
.
Dv(x1)/Dv(x2)
– this is the ratio between two percentiles.
.
ASD
– Arithmetic Standard Deviation, calculated as:
(
)
[
]
ASD
V d
Dv
i
i
=
-
å
( )
50
2
Where:
Vi=relative volume of band i and di=size of band i.
.
GSD
– Geometric Standard Deviation, calculated as:
(
)
[
]
GSD
V
d
Dv
i
i
=
-
å
exp
ln( ) ln(
( ))
50
2
Where:
Vi= relative volume of band i and di=size of band i.
.
Drr
– the Rosin-Rammler central size point (see below for details).
.
Nrr
– the Rosin-Rammler distribution width (see below for details).
.
Aux x1
– the Spraytec interface unit has a number of auxiliary ports. These
can be used to acquire a signal from other instruments. To view the signal
in the Size History view, select this variable type and specify the
x1
value,
the name of the instrument and the units in which the signal is displayed.
The
x1
value is the number of the auxiliary port the instrument is con-
nected to.
C H A P T E R 1 0
S
p
r
a
y
t
e
c
P a g e 1 0 . 3
Summary of Contents for Spraytec
Page 1: ...Spraytec User Manual Spraytec User Manual M A N 0 3 6 8 I s s u e 1 0 N o v 2 0 0 5...
Page 7: ...Part 1 Operator s guide Part 1 Operator s guide...
Page 8: ......
Page 9: ...Introduction to this manual Introduction to this manual C H A P T E R 1...
Page 10: ......
Page 16: ...C H A P T E R 1 S p r a y t e c Page 1 6 M A N 0 3 6 8...
Page 17: ...What is the Spraytec What is the Spraytec C H A P T E R 2...
Page 18: ......
Page 31: ...The Spraytec hardware The Spraytec hardware C H A P T E R 3...
Page 32: ......
Page 42: ...C H A P T E R 3 S p r a y t e c Page 3 10 M A N 0 3 6 8...
Page 43: ...The Spraytec software The Spraytec software C H A P T E R 4...
Page 44: ......
Page 63: ...Measurement tutorial Measurement tutorial C H A P T E R 5...
Page 64: ......
Page 99: ...Interpreting the results Interpreting the results C H A P T E R 6...
Page 100: ......
Page 125: ...Using measurement files Using measurement files C H A P T E R 7...
Page 126: ......
Page 133: ...Basic maintenance Basic maintenance C H A P T E R 8...
Page 134: ......
Page 139: ...Part 2 Supervisor s guide Part 2 Supervisor s guide...
Page 140: ......
Page 141: ...Security Security C H A P T E R 9...
Page 142: ......
Page 151: ...Advanced features Advanced features C H A P T E R 1 0...
Page 152: ......
Page 170: ...C H A P T E R 1 0 S p r a y t e c Page 10 18 M A N 0 3 6 8...
Page 171: ...SOP management SOP management C H A P T E R 1 1...
Page 172: ......
Page 175: ...Part 3 Appendices Part 3 Appendices...
Page 176: ......
Page 177: ...Health and Safety Health and Safety A P P E N D I X A...
Page 178: ......
Page 184: ...A P P E N D I X A S p r a y t e c Page A 6 M A N 0 3 6 8...
Page 185: ...Specification Specification A P P E N D I X B...
Page 186: ......
Page 191: ...Site requirements f r o m M A N 0 3 6 8 I s s u e 1 0 Site requirements A P P E N D I X C...
Page 200: ...A P P E N D I X D S p r a y t e c Page D 3 M A N 0 3 6 8...
Page 201: ...Installation Installation A P P E N D I X E...
Page 202: ......
Page 206: ...A P P E N D I X E S p r a y t e c Page E 4 M A N 0 3 6 8...
Page 207: ...Regulatory statements Regulatory statements A P P E N D I X F...
Page 208: ......
Page 213: ...Index Index...
Page 214: ......
Page 221: ......