background image

 

20 

 
 
 
 

12. CARRYING AND TRANSPORT

 

 
 

A) PLACING THE BOILER ON VEHICLE

 

 

 *When the boiler is placed placed on vehicle, loading should be with crane. 

  * Gates of the vehicle should be opened previously. 
  * Make use of the supporting ring while loading boiler with crane. 
  * Pass the crane boom hook from the supporting ring.  
  *Make sure that hook pim is in safety mode. 
  *Uphold the crane boom and take the space.  

*Slowly uphold the boiler that  bottom level should be 30-40cm up from the ground. 
*Keep away from sudden moves that would cause boiler to shake. 
*Move the boiler next  to vehicle in this way.   
*Lift the boiler from 30-40 cm higher than the vehicle body and take it down on vehicle body 
correctly. 
*Remove the hook from crane supporting ring. 

 

Attention

 : Boiler must be carried in vertical position, make use of the supporting ring. When 

the boiler is lifted up with crane, there shouldn't any living being under the boiler. Boiler must 
be carried with its accessories installed on it. 

 

B)  CARRYING BOILER ON VEHICLE 

 

 
When the boiler is carried with a vehicle, it should be tied to vehicle strictly, supporting stuff 
which would prevent slipping, should be put around. Boiler should not be carried with fragile, 
smashable and living beings. Top of the vehicle should be covered with canvas after placing 
boiler. Driver should  keep away from  sudden moves that would cause danger.

 

 

C) UNLOADING THE BOILER TO THE PLACE OF USE

 

Boiler should not be placed in work or residence places, should be placed in a seperate boiler 

room. 

When unloading the boiler to boiler room, crane must be used again, points that are stated in 

Clause A, should be considered. 

If the place of use is not appropriate for crane entrance, boiler should be unloaded in a proper 

place and carry with rollers to the place intended 

 

 

                        

 
             

Summary of Contents for 25 MKK-S

Page 1: ...1...

Page 2: ...TION AND WATER FLOOD 9 BOILER INSTALLATION SCHEMA 10 4 2 AIR CONNECTION 11 4 3 CHIMNEY 11 CHIMNEY CONNECTION SCHEMA 12 5 TECHICAL FEATURES 13 6 CONTROL PANEL 14 7 FIRST OPEATION AND USE 15 7 1 FIRST B...

Page 3: ...y and World market Our company which has acquired advanced technology and superior quality stands on in accordance with these principles This handbook is a helpful guide during operation and maintenan...

Page 4: ...strictly forbidden Please do not operate the boiler without water Do not feed cold water to hot boiler If for any reason the boiler temprature is over 90 degrees do not attempt to feed cold water to t...

Page 5: ...g and waiting time on the electronic control panel Detoriations as a result of burning are minimised thanks to cast iron burning bunker Fan with quiet running cycle period and clap ensures maximum eff...

Page 6: ...6 3 SECTIONS OF THE BOILER See techic table for dimensions stated with letters 5 6...

Page 7: ...r must be connected to a good drawing chimney and minimum number of elbows should be used between chimney and boiler Boiler must be placed at a location with enough air intake for an efificient burnin...

Page 8: ...om one end of the pipes and to drain off at the other side Circulation pump must be installed on boiler water return pipe During installation there must be enough working space left for technical serv...

Page 9: ...n of hot water must be provided by natural circulation The diameter of the pipe to be used at by pass line should be the same diameter size with the pipe used in installation at minimum As an extra se...

Page 10: ...10 BOILER INSTALLATION SCHEMA...

Page 11: ...ertical length must not be shorter than 60 cm and longer than 2 meters and pipe must be connected to the chimney with minimum 10 degree of angle We suggest not to use enamel stove pipes as it creates...

Page 12: ...the building if the chimney must pass from outside the isolation must be done properly The chimney must be frequently cleaned in order to avoid tar and soot and clogs Please avoid foreign objects cem...

Page 13: ...13 5 TECHNICAL SPECIFICATION...

Page 14: ...r fuel loading 04 255 sec Fuel feeding period setting button Sets fuel loading period 04 60 sec Fan Setting Button Sets speed level of fan From 1 to 5 Thermostat Setting Button Adjust the intended tem...

Page 15: ...iler lids must be closed and fan must be runned in low speed until the coal is completely combusted If fan blows too much air big slinders occurr because of the cooling effect of burning tank Make the...

Page 16: ...ses 5 C below set degree Running and stopping of circulation pump and fan can be monitored from flashing leds on digital indicator on control panel Circulation pump will run automatically for 3 second...

Page 17: ...nclogged Air holes must be cleaned up by turning on the fan for 15 minutes Electricity connection must be cut off before the maintainance Please ventilate the area before cleaning the boiler Electrici...

Page 18: ...18 10 ELECTRICITY SCHEMA...

Page 19: ...e comes from chimney connections Air holes which are inside the boiler can be blocked Clean up holes and smoke pipes regularly Boiler Chimney connections can be loosen Check the boiler chimney exit an...

Page 20: ...use of the supporting ring When the boiler is lifted up with crane there shouldn t any living being under the boiler Boiler must be carried with its accessories installed on it B CARRYING BOILER ON VE...

Reviews: