7. FIRST OPERATION AND USE
7.1 INITIAL BURNING
Before initial burning, system water must be full and system air must be purged.
Fuel loading must be done over the sifter. The sifter prevents the entrance of foreign objects, large
size coal pieces inside the reductor and damage reductor and helezon. Also it enables the passing of
the proper size of coal which will burn easily and efficiently
At initial burning, fan and reductor must be on and boiler water temprature must be previously set.
The reductor must be manually operated and fuel must be loaded to the combustion chamber. For
sufficient fuel loading,burnign pot must be loaded at the maximum level.
Small wood pieces must be ignited with gas and paper for burning the fuel in boiler. Then boiler
lids must be closed and fan must be runned in low speed until the coal is completely combusted. If
fan blows too much air, big slinders occurr because of the cooling effect of burning tank.
Make the fuel feeding and waiting settings according to boiler and fuel type from the Chart 1:
25.000
kcal/h
40.000
kcal/h
60.000
kcal/h
80.000
kcal/h
100.000
kcal/h
125.000
kcal/h
150.000
kcal/h
200.000
kcal/h
250.000
kcal/h
Coal 5000
kcal/h
Feeding
/sec)
4
6
9
12
15
19
24
32
40
Waiting
(sec)
106
110
116
116
122
130
138
156
174
Coal 7000
kcal/h
Feeding
/sec)
4
5
9
9
11
14
18
25
32
Waiting
(sec)
110
116
122
122
126
130
138
156
174
When the ignition is complete, make the reductor button on and operate the boiler with the
settings you did.
Increase the fan speed after ignition and provide the fuel efficiently.
It would be good to set the boiler water temperature at high degree
(70°C) from control panel.
Afterwards this temperature can be set to desired degree.