7. FIRST OPERATION AND USE

 

 

7.1 INITIAL BURNING

 

 

 
 

Before initial  burning, system water must be full and system  air must be purged. 
Fuel loading must be done over the sifter.  The sifter prevents the  entrance of foreign objects, large 
size coal pieces inside the reductor and damage reductor and helezon. Also it enables the passing of 
the proper size of coal which will burn easily and efficiently 
At initial burning, fan and reductor  must be on and boiler water temprature must be previously set. 
The reductor must be manually operated and fuel must be loaded to the combustion chamber. For 
sufficient fuel loading,burnign pot must be loaded at the maximum level.

 

 

Small wood pieces must be ignited with gas and paper for burning the fuel in boiler. Then boiler 
lids must be closed and fan must be runned in low speed until the coal is completely combusted. If 
fan blows too much air, big slinders occurr because of the cooling effect of burning tank.

 

 
Make the fuel feeding and waiting settings according to boiler and fuel type  from the Chart 1: 

 

 

 

25.000 

kcal/h 

40.000 

kcal/h 

60.000 

kcal/h 

80.000 

kcal/h 

100.000 

kcal/h 

125.000 

kcal/h 

150.000 

kcal/h 

200.000 

kcal/h 

250.000 

kcal/h 

Coal 5000 

kcal/h 

Feeding 

/sec) 

12 

15 

19 

24 

32 

40 

Waiting 

(sec) 

106 

110 

116 

116 

122 

130 

138 

156 

174 

Coal 7000 

kcal/h 

Feeding 

/sec) 

11 

14 

18 

25 

32 

Waiting 

(sec) 

110 

116 

122 

122 

126 

130 

138 

156 

174 

 
 

 
 

 

When the ignition is complete, make the reductor button on and  operate the boiler with the 
settings you did.

 

 Increase the fan speed after ignition and provide the fuel efficiently.

 

 

It  would  be  good  to  set  the  boiler  water  temperature  at  high  degree 

  (70°C)  from  control  panel. 

Afterwards this temperature can be set to desired degree.

 

 
 
 
 
 
 
 

Summary of Contents for 25 MKK-S

Page 1: ...1...

Page 2: ...TION AND WATER FLOOD 9 BOILER INSTALLATION SCHEMA 10 4 2 AIR CONNECTION 11 4 3 CHIMNEY 11 CHIMNEY CONNECTION SCHEMA 12 5 TECHICAL FEATURES 13 6 CONTROL PANEL 14 7 FIRST OPEATION AND USE 15 7 1 FIRST B...

Page 3: ...y and World market Our company which has acquired advanced technology and superior quality stands on in accordance with these principles This handbook is a helpful guide during operation and maintenan...

Page 4: ...strictly forbidden Please do not operate the boiler without water Do not feed cold water to hot boiler If for any reason the boiler temprature is over 90 degrees do not attempt to feed cold water to t...

Page 5: ...g and waiting time on the electronic control panel Detoriations as a result of burning are minimised thanks to cast iron burning bunker Fan with quiet running cycle period and clap ensures maximum eff...

Page 6: ...6 3 SECTIONS OF THE BOILER See techic table for dimensions stated with letters 5 6...

Page 7: ...r must be connected to a good drawing chimney and minimum number of elbows should be used between chimney and boiler Boiler must be placed at a location with enough air intake for an efificient burnin...

Page 8: ...om one end of the pipes and to drain off at the other side Circulation pump must be installed on boiler water return pipe During installation there must be enough working space left for technical serv...

Page 9: ...n of hot water must be provided by natural circulation The diameter of the pipe to be used at by pass line should be the same diameter size with the pipe used in installation at minimum As an extra se...

Page 10: ...10 BOILER INSTALLATION SCHEMA...

Page 11: ...ertical length must not be shorter than 60 cm and longer than 2 meters and pipe must be connected to the chimney with minimum 10 degree of angle We suggest not to use enamel stove pipes as it creates...

Page 12: ...the building if the chimney must pass from outside the isolation must be done properly The chimney must be frequently cleaned in order to avoid tar and soot and clogs Please avoid foreign objects cem...

Page 13: ...13 5 TECHNICAL SPECIFICATION...

Page 14: ...r fuel loading 04 255 sec Fuel feeding period setting button Sets fuel loading period 04 60 sec Fan Setting Button Sets speed level of fan From 1 to 5 Thermostat Setting Button Adjust the intended tem...

Page 15: ...iler lids must be closed and fan must be runned in low speed until the coal is completely combusted If fan blows too much air big slinders occurr because of the cooling effect of burning tank Make the...

Page 16: ...ses 5 C below set degree Running and stopping of circulation pump and fan can be monitored from flashing leds on digital indicator on control panel Circulation pump will run automatically for 3 second...

Page 17: ...nclogged Air holes must be cleaned up by turning on the fan for 15 minutes Electricity connection must be cut off before the maintainance Please ventilate the area before cleaning the boiler Electrici...

Page 18: ...18 10 ELECTRICITY SCHEMA...

Page 19: ...e comes from chimney connections Air holes which are inside the boiler can be blocked Clean up holes and smoke pipes regularly Boiler Chimney connections can be loosen Check the boiler chimney exit an...

Page 20: ...use of the supporting ring When the boiler is lifted up with crane there shouldn t any living being under the boiler Boiler must be carried with its accessories installed on it B CARRYING BOILER ON VE...

Reviews: